05.04.2013 Views

The Nimrod Review - Official Documents

The Nimrod Review - Official Documents

The Nimrod Review - Official Documents

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

<strong>The</strong> <strong>Nimrod</strong> <strong>Review</strong><br />

48<br />

4.24<br />

Figure 4.7: Old Section of Cross Feed Duct<br />

Although, in theory, the <strong>Nimrod</strong>’s hot air duct insulation was intended to be liquid-proof, there were a number<br />

of weaknesses in its design. <strong>The</strong>se weaknesses stemmed from the fact that the Refrasil was not continuous<br />

and did not cover every inch of the ducting; therefore, parts of the duct, in particular some expansion bellows,<br />

were left unlagged or covered in ‘shrouds’ or ‘laced muffs’, which were vulnerable to fluid ingress (see further<br />

below).<br />

Unlagged Bellows<br />

4.25<br />

4.26<br />

<strong>The</strong>re are a number of un-insulated bellows within the Cross-Feed/SCP duct system. <strong>The</strong> BOI was unable to<br />

determine any recorded reason for leaving the bellows in the upper No. 7 Tank Dry Bay un-insulated. Trials<br />

conducted by the BOI recorded that these bellows reached a temperature of between 343°C and 399°C when<br />

the Cross-Feed duct was open. 29 As noted above, these trials were limited by restrictions placed on the operation<br />

of the SCP after the loss of XV230 and full operating temperatures could not be reached. <strong>The</strong> temperature<br />

of the bellows when the SCP operated in the air would be higher. Indeed, from the BAE Systems and AAIB<br />

evidence quoted previously, the duct could have reached temperatures in excess of 400°C.<br />

BAE Systems has been unable to trace a positive design decision to leave the No. 7 Tank Dry Bay bellows<br />

un-insulated. This is perhaps not surprising in view of the passage of time since the original design was<br />

completed. BAE Systems submitted to the <strong>Review</strong>, however, that the decision not to insulate the bellows was an<br />

“understandable and a reasonable engineering judgement”. 30 This was based on five main assertions: 31<br />

(1) As the bellows are situated above the fuel pipework in the No.7 Tank Dry Bay leaking fuel is unlikely to<br />

impinge on them;<br />

(2) Although the bellows are below elements of the aircraft’s vent system, this system will only hold limited<br />

amounts of fuel in the event of a system ‘abnormality’;<br />

(3) <strong>The</strong> AIT for AVTUR is likely to be higher than the surface temperature of the bellows;<br />

(4) Any leak of fuel reaching the bellows would be unlikely to be sufficient for a sustained fire; and<br />

(5) Fitting a detachable insulating muff would have added a potential loose article hazard to an area crowded<br />

with flight control cables and pulleys.<br />

29 BOI Report, Exhibit 36.<br />

30 BAE Systems written submissions to the <strong>Review</strong>.<br />

31 BAE Systems written submissions to the <strong>Review</strong>.<br />

Example of compressed insulation<br />

found in the No 7 Tank Dry Bay

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!