05.04.2013 Views

The Nimrod Review - Official Documents

The Nimrod Review - Official Documents

The Nimrod Review - Official Documents

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

<strong>The</strong> <strong>Nimrod</strong> <strong>Review</strong><br />

418<br />

significant safety margin to prevent blow-off. This 10,000lbs limit remained in force notwithstanding that the<br />

original problem had been caused by an incorrectly constructed fuel tank.<br />

Enhanced fuel and vent system maintenance regimes: 2007<br />

15.12<br />

14 An independent fuel system hazard analysis carried out by QinetiQ identified the requirement to inspect the<br />

fuel system in a number of areas not previously considered. 15 Pressure testing of the fuel system vent pipes was<br />

also introduced, to check and ensure their integrity. 16<br />

XV235: November 2007 incident led to total cessation of AAR<br />

15.13<br />

In November 2007, whilst carrying out AAR from a Tristar over Afghanistan, XV235 experienced a fuel leak in<br />

the bomb bay. A crew member noticed what appeared to be a spray of fuel emitting from the fuel system and,<br />

in view of the crew’s understanding of what had occurred to XV230, the aircraft issued a Mayday and diverted<br />

to Kandahar. <strong>The</strong> aircraft was examined on landing and traces of fuel in the bomb bay confirmed that there had<br />

indeed been a leak. However, despite extensive trials, the aircraft’s engineers were unable to replicate the leak<br />

on the ground. <strong>The</strong> inability to reproduce the leak, even when subjecting the fuel system to pressures similar<br />

to those experienced during AAR, meant that there could be no guarantee that leaks could be detected during<br />

pre-flight inspections. <strong>The</strong> increased risk to the <strong>Nimrod</strong> crews should they continue flying AAR sorties was<br />

balanced against the increased risk to ground forces inherent in any reduction in <strong>Nimrod</strong> coverage concomitant<br />

on a cessation of AAR. Following considered analysis of the issue, the AOA decided that <strong>Nimrod</strong> AAR should<br />

cease. It should be noted that, during the investigation into XV235, an Avimo coupling was dismantled and<br />

was found to have a pipe-to-pipe gap which was outside specified limits. A leak had been noticed from it by<br />

the ground crew at about 1 drip per minute and so it was thought unlikely to have been the cause of the leak<br />

seen in the air.<br />

BOI recommendations implemented from December 2007 onwards<br />

15.14<br />

15.15<br />

<strong>The</strong> BOI made a total of 33 formal recommendations in its Report which was published on 4 December<br />

2007. 28 of the BOI’s recommendations were accepted. Five of the BOI’s recommendations were rejected. Of<br />

these, the effect of three was achieved by an alternative course of action. Of the remaining two, a study was<br />

undertaken into the utility of parachute escape from the <strong>Nimrod</strong>, but it was decided that any solution could not<br />

be incorporated within the remaining life of the aircraft; a similar decision was made as to the recommendation<br />

to fit a crash protected means of recording position and intercom voice. <strong>The</strong> most recent update on progress<br />

with the BOI’s recommendations is to be found at Appendix A at the end of this Chapter.<br />

Implementation of the BOI’s formal recommendations began in December 2007. Amongst the first of these was<br />

the inclusion of more detailed information within the aircraft’s Topic 1 engineering manuals on the assembly<br />

of FRS and AVIMO fuel system couplings. A number of the BOI recommendations, such as the review of<br />

maintenance policy, a review of the <strong>Nimrod</strong> Safety Case to correct errors within it and the conduct of an Ageing<br />

Aircraft Systems Audit (AASyA), 17 were extensive tasks and it was realised that they would take some time to<br />

complete. As the <strong>Review</strong> went to publication, it was predicted that all remaining recommendations, with the<br />

exception of the Safety Case <strong>Review</strong>, would be completed by the end of October 2009. <strong>The</strong> Safety Case <strong>Review</strong><br />

has resulted in the production of Safety Case 3 (SC3), as explained further below.<br />

14 <strong>Nimrod</strong> Fuel System Safety <strong>Review</strong> Report QINETIQ/EMEA/IX/SCRO702915.<br />

15 RTI 207.<br />

16 RTI 196.<br />

17 BOI Recommendation 2 at paragraph 65 a (2) of the BOI Report.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!