05.04.2013 Views

The Nimrod Review - Official Documents

The Nimrod Review - Official Documents

The Nimrod Review - Official Documents

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

Chapter 11 – <strong>Nimrod</strong> Safety Case: Analysis and Criticisms<br />

(3) <strong>The</strong> Mech Systems Pro-Forma stated that “the Bleed ducting is insulated and so surface temperatures<br />

will be below bleed air temperatures” but failed to note that: (a) there were gaps between the insulation;<br />

(b) some parts of the bleed ducting have no insulation; and (c) the insulation was in poor condition in<br />

some areas.<br />

(4) <strong>The</strong> Mech Systems Pro-Forma stated that “From in-service data the potential for fuel pipe leakage<br />

is given as Improbable”. I have already discussed above: (a) the obviously erroneous nature of this<br />

assumption; (b) the fact that anyone familiar with <strong>Nimrod</strong> maintenance would have known that it was<br />

erroneous; and (c) the inappropriateness of using MRA4 generic data in the first place.<br />

(5) <strong>The</strong> Mech Systems Pro-Forma stated that “From in-service data the potential for bleed air duct leakage<br />

is given as Improbable”. BAE Systems confirmed to the <strong>Review</strong> that this assessment was also based<br />

on the generic MRA4 data, which gave a failure probability for ECS 45 pipes and clamps as 2E -7 (i.e.<br />

2 x 10 -7 ), and for ECS pipe seals as 1.5E-7 (i.e. 1.5 x 10 -7 ). <strong>The</strong> author of the Hazard H73 Pro-Forma,<br />

used these generic failure probabilities in his assessment of bleed air duct leakage in order to conclude<br />

that the risk of bleed air duct leakage was within the range of 1 x 10 -6 to 1 x 10 -7 (i.e. “Improbable”).<br />

As stated above, however, this assessment ignored both the early BAe reports of the 1980s and the<br />

evidence presented to the <strong>Review</strong> which clearly shows that there was a significant history of hot air duct<br />

leakages (see Chapter 7). Against this background, it is most difficult to see how a categorisation of<br />

“Improbable” could ever have been appropriate.<br />

(6) <strong>The</strong> Mech Systems Pro-Forma failed to pick up on the zonal risk presented by the location and proximity<br />

of the starboard blow-off valve immediately forward of the No. 7 Tank Dry Bay, such that fuel expelled<br />

from the blow-off valve could track back into the No. 7 Tank Dry Bay and ignite.<br />

BAE Systems’ arguments<br />

Fire zone<br />

11.115 BAE Systems argued that there was nothing in the Pro-Forma for Hazard H73 which would suggest that Zone<br />

614 should be treated as a “fire zone”. This is, however, to ignore: (a) section 4L which specifically cites the<br />

requirement of AvP 970 that anywhere where a “single point failure” could lead to a fire should be treated as a<br />

“fire zone”; and (b) section 3 which sets out no less than 15 different “single point failure” scenarios which could<br />

lead to catastrophic fire, explosion or overheating. In my judgment, there is no doubt that Zone 614 should have<br />

been identified and treated as a ‘fire zone’. <strong>The</strong> factual inaccuracies led, however, to the author ignoring, or<br />

otherwise discounting, the actual risk represented by the Cross-Feed/SCP duct as a serious ‘live’ ignition source<br />

and the risk of a fuel or hydraulic leak onto the Cross-Feed/SCP duct as a single point failure.<br />

Ignition source probability<br />

11.116 <strong>The</strong>re were repeated suggestions from various BAE Systems witnesses, including Witness R [BAE Systems] himself,<br />

that when drawing up section 6 of the Pro-Forma for Hazard H73 a ‘worst case’ scenario for the ignition source<br />

was assumed, i.e. a probability of ‘1’, on the basis that the Cross-Feed/SCP duct was un-insulated and ‘live’ all<br />

the time. In my judgment, this was another piece of ex post facto rationalisation by BAE Systems designed to<br />

downplay the significance, in particular, of the most glaring factual error in the Pro-Forma namely, the statement<br />

that “....the duct is only pressurised when the cross-feed valve is open, i.e. during engine start” (on the ground),<br />

when, in fact, the Cross-Feed/SCP duct was routinely used in flight to power the SCP or to re-start engines after<br />

shut-down in flight. If a probability of ‘1’ had been assumed for the ignition source, there would have been<br />

no need for any detailed analysis of the Cross-Feed/SCP duct, when it was open or shut, or whether it was<br />

insulated or not. It should be noted that, in section 6 of the Pro-Forma for Hazard H73, Witness R [BAE Systems]<br />

went on to refer specifically to the “extreme” situation when the Cross-Feed/SCP duct would be supplied by the<br />

engines on “full power” on a hot day but discounted the risk because “...analysis has shown that the surface<br />

temperature of the insulation in all cases will be below that required for spontaneous combustion of the fuel”.<br />

45 Bleed-air has a number of uses, one of which is to supply the environmental control systems which feed air into the aircraft cabin.<br />

289

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!