05.04.2013 Views

The Nimrod Review - Official Documents

The Nimrod Review - Official Documents

The Nimrod Review - Official Documents

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

<strong>The</strong> <strong>Nimrod</strong> <strong>Review</strong><br />

7.39<br />

142<br />

combination of consistently pessimistic Design Authority predicted lives for the hot air ducts and a minimal<br />

number of failures detected during inspection 47 seems to have engendered an atmosphere of ennui among<br />

those responsible for ensuring the integrity of the hot air system, such that no positive action had been taken to<br />

resolve and explain the discrepancy in views. However, while rejecting the duct lives determined by BAE Systems<br />

in June 2005, the <strong>Nimrod</strong> IPT was nonetheless convinced that the ducts should be lifed, but that more credible<br />

figures should be determined. As a result, BAE Systems was tasked with further work (see below).<br />

As regards the UI’s recommendation that a hot air leak warning system should be introduced for the duct which<br />

failed on XV227 and for the Cross-Feed bleed air-duct, even following the UI Report, the IPT continued to hold<br />

the view (relying on the presence of the centre section overheat detectors) that the only duct not covered by<br />

such a system was the one that had failed on XV227 and which was subsequently being replaced throughout<br />

the fleet. 48 In any event, the IPT ultimately decided not to proceed with the proposed warning system, on the<br />

basis that it was not practicable to do so given the length of time it would take to introduce such a modification<br />

into service compared against the MR2’s OSD. 49 As mitigation in support of this decision, the IPT noted that the<br />

aircrew procedures in relation to SCP malfunctions had been amended so as to increase awareness of SCP duct<br />

failures.<br />

Further investigations into the life of the ducts<br />

7.40<br />

7.41<br />

<strong>The</strong> IPT did, however, adopt the other recommendations of the UI into XV227, including that the ducting which<br />

had been removed from XV227 should be the subject of a test programme in order better to inform decisions<br />

on a safe life for each duct. BAE Systems was tasked to carry out this exercise. From late December 2006 into<br />

2007, BAE Systems issued a number of reports to the <strong>Nimrod</strong> IPT with the results of its pressure testing and<br />

examination of the ducts. 50 At a strategy meeting held at BAE Systems Chadderton on 20 February 2007, it was<br />

agreed that that BAE Systems would categorise the different sections of duct identified in its June 2005 report<br />

according to the likelihood of significant collateral damage to fuel pipes and tanks in the event of duct failure,<br />

and therefore the priority for their replacement. It was further agreed that BAE Systems would provide the IPT<br />

with a lifing policy for all of the relevant ducts.<br />

51 BAE Systems reported back to the IPT in a letter dated 8 March 2007, setting out its conclusions in relation<br />

to these two tasks. A replacement category of 1 (i.e. the most important) was attributed to the ducting which<br />

was close to the No. 7 fuel tank, and also to ducting which was close to fuel pipes in Rib 2. For the vast majority<br />

of the ducts, a safe life of 2,500 flying hours was given. For reasons which remain obscure, the <strong>Nimrod</strong> IPT did<br />

not receive a copy of BAE Systems’ February or March 2007 reports until June 2007 (and hence these were<br />

not available to the BOI when preparing its report on XV230). Subsequently, in response to an IPT request<br />

for clarification dated 3 December 2007, BAE Systems confirmed that its lifing policy recommendation also<br />

covered non-critical, non-bellowed ducts and that its intent was that the life of all ducts in the system should<br />

be the same, i.e. lifed at 2,500 flying hours. This decision was agreed between the IPT and BAE Systems, based<br />

on a combination of BAE Systems’ theoretical calculations and the results of tests on actual ducts. <strong>The</strong> life is<br />

significantly greater than the purely theoretical figures previously quoted, but also significantly less than the life<br />

displayed by the great majority of the aircraft’s hot air ducts. <strong>The</strong> simple fact is that, having been replaced, the<br />

ducts will not need further replacement within the predicted life of the remaining <strong>Nimrod</strong>s.<br />

47 This attitude does appear to be contradicted by an IPT generated document following the XV227 incident which states: “many ducts have already<br />

been changed across the fleet due to leaks from the bellows or corrosion”: ES(Air)(WYT)/512752/8, dated 6 October 2005.<br />

48 See the IPT’s memo on the “Supplementary Cooling Pack Damage Sustained by <strong>Nimrod</strong> MR2 XV227 – Unit Inquiry Recommendations”, ES (Air)/<br />

(WYT)512752/8, dated 6 October 2005.<br />

49 “XV227 Hot Air Duct Failure – Requirement for Leak Detection System”, DLO (Strike) (Wyt)/512752/21/227, dated 5 July 2006; BOI Report, Exhibit<br />

24. In fact, the Out-of-Service Date was at the time 2010, not 2012.<br />

50 e.g. Letter “<strong>Nimrod</strong> – Testing of Hot Air Ducts Removed from XV227” dated 8 December 2006 and BAE Systems’ Document No. CHD-TFM-R-ISA-<br />

MB1486 “Pressure Testing and Examination of <strong>Nimrod</strong> Hot Air Ducts taken from Aircraft XV227 and XV228”, dated 28 February 2007.<br />

51 BAE Systems’ Reference: FAT/801R/07/009

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!