05.04.2013 Views

The Nimrod Review - Official Documents

The Nimrod Review - Official Documents

The Nimrod Review - Official Documents

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Serial<br />

Recommendations Status<br />

Number<br />

3 <strong>The</strong> <strong>Nimrod</strong> Safety Case (SC) is reviewed, reassessing the Action Continuing.<br />

factual data used for interpretation and categorization<br />

<strong>Review</strong> commenced by BAES on 3 Dec 07 and initial target completion date was Apr 08. However,<br />

of hazard and risk. <strong>The</strong> review should include widespread<br />

as work progressed it became clear that the review would require more extensive effort than<br />

operator (air and ground crew) involvement. This work<br />

initially planned. <strong>The</strong> changing strategy imposed additional work and concomitant delays in<br />

should be incorporated within the review of <strong>Nimrod</strong><br />

completion dates. BAES estimated that they would be unable to complete the SC until 2010.<br />

maintenance policy.<br />

Although the SC review is not yet complete the <strong>Nimrod</strong> MR2 Safety Engineer, supported by the<br />

PSEWG, is confident that the wide-ranging, complementary, independent studies, and the XV<br />

236 tear-down, have provided enough information for him to confirm that the <strong>Nimrod</strong> remains<br />

safe to operate. In addition no evidence has been produced from the ongoing work on the SC<br />

that would call into question <strong>Nimrod</strong> airworthiness.<br />

Nonetheless, in view of the delays in the provision of the SC, the <strong>Nimrod</strong> Team has developed<br />

an alternative means of completion. <strong>The</strong> <strong>Nimrod</strong> Team has been working with QinetiQ to<br />

produce a SC (based on a model successfully completed for the BBMF), whilst still using BAES<br />

information where available. <strong>The</strong> <strong>Nimrod</strong> Team approach was endorsed during the D AS <strong>Nimrod</strong><br />

2* Airworthiness <strong>Review</strong> held on 21 Jul 09.<br />

<strong>The</strong> <strong>Nimrod</strong> PT Project Engineer reported to an Extraordinary meeting of the PSEWG on 2 Oct 09<br />

that he intended to recommend to the RTSA that the <strong>Nimrod</strong> Equipment Safety Case (ESC) be<br />

accepted.<br />

<strong>The</strong> ESC will now be independently reviewed. This review will comprise 2 elements. <strong>The</strong> Independent<br />

Safety Audit (auditing the structure, method and logic of the safety case) will take approximately<br />

6 week. However, an Independent Technical Evaluation of BAES’s zonal and functional hazard<br />

analysis (which is a major contributor to the equipment safety case) will be conducted in parallel<br />

and is estimated to require 8 – 12 weeks. While these tasks are underway the <strong>Nimrod</strong> PSEWG<br />

agrees that work already completed will continue to support the safe operation of the <strong>Nimrod</strong>.<br />

Appendix A to Chapter 15<br />

Final confirmation of the integrity, accuracy and applicability of the ESC will be provided by<br />

this process and, thus, this action will remain open until both independent checks have been<br />

completed.<br />

431

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!