05.04.2013 Views

The Nimrod Review - Official Documents

The Nimrod Review - Official Documents

The Nimrod Review - Official Documents

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

Chapter 11 – <strong>Nimrod</strong> Safety Case: Analysis and Criticisms<br />

CRITICISMS OF THE NIMROD IPT in relation to the <strong>Nimrod</strong> Safety Case<br />

Introduction<br />

11.171 In my judgment, the <strong>Nimrod</strong> IPT bears considerable responsibility for the lamentable quality of the NSC and the<br />

singular failure of the NSC to capture the catastrophic fire risk presented by the Cross-Feed/SCP duct risk. If the<br />

<strong>Nimrod</strong> IPT had performed its duties in relation to the NSC appropriately and carefully, it is likely that the NSC<br />

would have properly identified, assessed and addressed this fire risk and the loss of XV230 would have been<br />

avoided.<br />

11.172 <strong>The</strong> <strong>Nimrod</strong> IPT was responsible for ensuring the safe through-life management of the <strong>Nimrod</strong> fleet. Safety<br />

Cases were mandated by BP1201. <strong>The</strong> <strong>Nimrod</strong> IPT outsourced the task of preparing the NSC to BAE Systems<br />

(see further below). It was, therefore, the <strong>Nimrod</strong> IPT’s responsibility to project manage the task and ensure that<br />

a proper Safety Case was produced for the <strong>Nimrod</strong> fleet. QinetiQ acted as ‘independent advisor’ in relation to<br />

the NSC and supported the sign-off of the NSC. <strong>The</strong> <strong>Nimrod</strong> IPT finally completed the NSC in February 2005.<br />

11.173 As explained above and in Chapter 10A, there were significant flaws in the NSC which was produced in the<br />

period 2001 to 2005. <strong>The</strong> NSC failed to identify the serious fire risk in No. 7 Tank Dry Bay starboard which the<br />

Cross-Feed/SCP duct posed to the <strong>Nimrod</strong> fleet (Hazard H73) and which subsequently caused the loss of XV230<br />

in September 2006.<br />

11.174 As explained above, the <strong>Review</strong> identified a number of errors in the NSC in relation to Hazard H73 alone and<br />

decided to conduct a detailed investigation into the entire NSC and found: First, the errors identified by the BOI<br />

and the <strong>Review</strong> in relation to Hazard H73 were not one-off, but appear to have been symptomatic of a generally<br />

poor standard of accuracy and analysis in the NSC. Second, the NSC Baseline Safety Case Reports (BLSC Reports)<br />

produced by BAE Systems left over 30% of the hazards “Unclassified” and 40% of the hazards remained<br />

“Open”, many with no recommendation beyond simply that “Further analytical techniques are required” before<br />

they could be categorised, sentenced and closed. Third, the Fire & Explosion Report did not accord with the BLSC<br />

Reports produced by BAE Systems. Fourth, the NSC had not reduced the risks to the <strong>Nimrod</strong> fleet to ALARP. 102<br />

11.175 Unfortunately, the <strong>Nimrod</strong> IPT failed to grasp the opportunity which then presented itself properly to categorise<br />

and mitigate catastrophic Hazard H73.<br />

Key Personnel<br />

11.176 <strong>The</strong> key personnel in the <strong>Nimrod</strong> IPT with responsibilities for the NSC were: (1) the <strong>Nimrod</strong> IPT Leader (IPTL),<br />

Group Captain (now Air Commodore) George Baber, who was also the <strong>Nimrod</strong> Project Engineer (PE); (2) the<br />

Head of Air Vehicle, Wing Commander Michael Eagles, and (3) the Safety Manager, Frank Walsh (see further<br />

below). References hereafter to the <strong>Nimrod</strong> IPT are generally to these key personnel.<br />

Lack of guidance<br />

11.177 As set out in Chapter 9, JSP318B prescribed a Safety Management System (SMS) for military aircraft and set<br />

out the aims and objectives of such a system. Whilst JSP318B mandated a clear policy, it is fair to say that the<br />

majority of the MOD personnel required to implement that policy had received little (if any) relevant guidance<br />

and training, and nor was it clear to them where they were meant to look for support. <strong>The</strong> IPTs felt they<br />

lacked advice and guidance generally regarding safety matters. A Safety Process <strong>Review</strong> in 2002 initiated by the<br />

Defence Procurement Agency reported: “<strong>The</strong> universal plea was for early, authoritative advice on what had to<br />

be done, by whom, when and in what format with regard to safety on their project”. 103 <strong>The</strong> lack of practical<br />

guidance does not, however, excuse the basic failures of the <strong>Nimrod</strong> IPT to follow its own procedures or ensure<br />

the safety of the <strong>Nimrod</strong> fleet.<br />

102 i.e. Risks were not reduced to As Low As Reasonably Practicable (see Chapter 9).<br />

103 Safety Process <strong>Review</strong>, dated 23 December 2002, Advantage Technical Consulting: Section 3 Interview Phase, paragraph 3.2 on IPTs, especially<br />

paragraph 3.2.2.<br />

305

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!