05.04.2013 Views

The Nimrod Review - Official Documents

The Nimrod Review - Official Documents

The Nimrod Review - Official Documents

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Chapter 11 – <strong>Nimrod</strong> Safety Case: Analysis and Criticisms<br />

up most of the time negotiating the second <strong>Nimrod</strong> Integrated Support Contract (NISC 2) with BAE Systems<br />

and simply “didn’t have the time to be hands on” in relation to the NSC. Sixth, the NSC is symptomatic of a<br />

widespread malaise of the ‘tick box’ mentality, whereby reports are outsourced to consultants and, on receipt,<br />

simply put in a drawer without being read or checked, and the relevant box ticked.<br />

11.212 It must also be remembered that the Pro-Formas under-pinning the NSC were not readily available to the<br />

<strong>Nimrod</strong> IPT (or QinetiQ) at the time that the six NSC reports were delivered to them, as they were only accessible<br />

from the BAE Systems terminal at Chadderton. This, however, does not excuse the failure of George Baber,<br />

Michael Eagles and Frank Walsh to call for the production of any of the mitigating evidence behind the NSC<br />

Reports produced by BAES, or to ensure that such evidence was carefully checked by the relevant <strong>Nimrod</strong> IPT<br />

engineering specialists, Heads of Branch and QinetiQ as the <strong>Nimrod</strong> IPT’s independent advisor in relation to the<br />

project. Had they done so, I have no doubt that they would have uncovered that the Pro-Formas prepared by<br />

BAE Systems included numerous errors of fact and analysis, including the Pro-Forma in relation to Hazard H73.<br />

(6) <strong>The</strong> <strong>Nimrod</strong> IPT subsequently signed off BAE Systems’ NSC task in circumstances<br />

where it was inappropriate to do so.<br />

11.213 In my judgment, the <strong>Nimrod</strong> IPT subsequently signed off BAE Systems’ NSC task in circumstances where it was<br />

inappropriate to do so. <strong>The</strong> formal sign-off followed the Sixth PSWG meeting on 10 November 2004, where the<br />

<strong>Nimrod</strong> IPT’s earlier lack of activity was repeated.<br />

Sixth PSWG meeting on 10 November 2004<br />

11.214 On 10 November 2004, George Baber chaired the Sixth PSWG meeting at RAF Wyton. On behalf of BAE<br />

Systems, Chris Lowe and Richard Oldfield, gave a PowerPoint presentation regarding the BLSC in which he<br />

said all foreseeable hazards had been “identified and assessed, and addressed... [and] eliminated or reduced to<br />

[ALARP]..” and that “...where the existing level of mitigation against a hazard was determined as insufficient/<br />

incomplete, the report conclusions contain recommendations”. <strong>The</strong>re was also a brief demonstration by Witness<br />

C [BAE Systems] of how the CASSANDRA Hazard Log worked.<br />

11.215 Again, the BAE Systems’ representatives did not go into any relevant details as to how much of the Phase 2<br />

project had been completed and what remained to be done, and did not volunteer precisely how many hazards<br />

remained “Open” or “Unclassified”.<br />

11.216 Again, the <strong>Nimrod</strong> IPT representatives present (including the IPTL, George Baber) were content to sit, passively,<br />

and accept at face value the PowerPoint presentations by BAE Systems. <strong>The</strong>y did not raise any queries in relation<br />

to what was presented by BAE Systems or ask BAE Systems any of the intelligent questions which should have<br />

been asked. Instead, George Baber simply thanked BAE Systems for its work in producing the Safety Case<br />

Report and Hazard Log and Frank Walsh was tasked to produce a document and a suitable date for the IPTL<br />

formally to ‘sign-off’ the NSC, which he formally did on 15 December 2004.<br />

11.217 In his written submissions to the <strong>Review</strong>, George Baber sought to suggest that this was not the sort of meeting<br />

where detailed questioning of BAE Systems on their work would have been ‘feasible or appropriate’ and it was<br />

never intended that the NSC task would be formally accepted at the Sixth PSWG meeting “and indeed, it was<br />

not”. This does not square, however, either with the minutes or with his letter of 15 December 2004 in which<br />

he expressly referred to the fact of ‘acceptance’ of the NSC Reports ‘at’ the Sixth PSWG. Moreover, it would not<br />

have required detailed questioning of BAE Systems to elicit that there was a large hole in its work. 115<br />

115 George Baber’s suggestion that, whilst 43 “Open” hazards out of 105 is a high proportion, it is not a large proportion when compared with an<br />

original total of “2,000 open hazards in Phase 1” betrays a misunderstanding of the Phase 2 rationalisation of hazards.<br />

313

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!