05.04.2013 Views

The Nimrod Review - Official Documents

The Nimrod Review - Official Documents

The Nimrod Review - Official Documents

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

<strong>The</strong> <strong>Nimrod</strong> <strong>Review</strong><br />

10A.15<br />

194<br />

<strong>The</strong> essential aim of the NSC was straightforward, as the <strong>Nimrod</strong> IPT explained to BAE Systems at an early<br />

meeting on 1 August 2001: “A Safety Case should be a safety argument which highlights risks.”<br />

4 October 2001: Internal BAE Systems meeting<br />

10A.16<br />

10A.17<br />

On 4 October 2001, an internal BAE Systems meeting was held at Warton to discuss the requirements of PDS<br />

Task AV(PDS)814. 12 <strong>The</strong> file note of that meeting13 records a number of points of discussion. First, the MOD<br />

were looking to spend only c. £100,000 – £200,000 over a period of six months on the NSC, whereas the<br />

Harrier ‘Safety Case’ cost £3 million and took over two years. This apparent concern as to the limited budget<br />

did not seem to be taken further. Second, it was agreed that BAE Systems should assist the MOD to develop<br />

‘strategies’ for the development of the NSC. Third, it was agreed that BAE Systems should suggest to the<br />

MOD that the PDS Task ought to be re-written to read: “Construct the explicit Safety Case by documenting<br />

the Implicit Safety Case, using the Strategy developed in 1a above.” This amendment was never, in fact,<br />

made; but it does encapsulate BAE Systems’ essential (flawed) approach to the task (see further below).<br />

Fourth, hazards with ‘seemingly unacceptable’ Hazard Risk Indices could be considered ‘acceptable’ based<br />

on 20 years historical evidence ‘as per the Harrier Safety Case’. Fifth, it ‘may be possible’ to use the <strong>Nimrod</strong><br />

MRA4 Hazard Log and Accident Model as a starting point for the NSC.<br />

Three of these suggestions are of particular concern, and bear the seeds of the flawed approach to the NSC<br />

adopted by BAE Systems which was subsequently to bedevil its production:<br />

10A.17.1 First, the suggestion that the PDS Task ought to be re-written to read “Construct the explicit<br />

Safety Case by documenting the Implicit Safety Case...” 14 is illuminating. It indicates that, from<br />

the very beginning, BAE Systems viewed the process of constructing an “explicit” Safety Case<br />

as one of just documenting the “implicit” Safety Case, i.e. it was essentially a documentary or<br />

paperwork exercise, in which the hazards were more theoretical than real, the object being<br />

merely to populate the ‘CASSANDRA’ database. 15<br />

10A.17.2 Second, the suggestion that hazards with “seemingly unacceptable” Hazard Risk Indices could<br />

nevertheless “be considered for acceptance based on 20 years historical evidence, as per Harrier<br />

Safety Case”, gives cause for concern. It indicates a flawed mindset for legacy aircraft: ‘if it has not<br />

happened in the past, it is unlikely to happen in the future’. Further, as will be seen, the <strong>Nimrod</strong><br />

fleet did not have sufficient total flight hours to provide a satisfactory historical incident base.<br />

10A.17.3 Third, the suggestion that it might be possible to use the <strong>Nimrod</strong> MRA4 Hazard Log as a “starting<br />

point” for a Safety Case for the MR2 and R1 was misconceived. <strong>The</strong> <strong>Nimrod</strong> MRA4 was a new<br />

build prototype. It was based on the <strong>Nimrod</strong> fuselage but was essentially a new aircraft. Its<br />

systems had little in common with the MR2 and R1 and it was unlikely to prove a reliable basis<br />

for a safety case for its 30-year-old predecessors (as, indeed, Chris Lowe of BAE Systems himself<br />

later acknowledged). 16<br />

9 October 2001: QinetiQ Task <strong>Review</strong> Meeting<br />

10A.18<br />

17 At a QinetiQ Task <strong>Review</strong> Meeting (TRM) on 9 October 2001, it was suggested that the <strong>Nimrod</strong> IPT might<br />

task QinetiQ to review the draft <strong>Nimrod</strong> SMP and take on the role of an “Independent Safety Auditor”.<br />

An “Independent Safety Auditor” was defined in Defence Standard (Def-Stan) 00-56 (Part 1)/3 Annex A<br />

(Definitions), dated 19 December 2004 as:<br />

12 BAE Systems Task No. 16-3151.<br />

13 File Note written by the Airworthiness/Regulations Manager – FSTA, 4 October 2001.<br />

14 Strategy item 1c on the PDS Task AV(PDS)814.<br />

15 Cassandra (´ ) was the beautiful daughter of King Priam and Queen Hecuba of Troy. Apollo granted her the gift of prophecy but, when<br />

she spurned his love, he placed upon her the curse that no-one would ever believe her predictions.<br />

16 At the First PSWG Meeting on 18 March 2003.<br />

17 QinetiQ Task <strong>Review</strong> Meetings were held regularly (mostly quarterly) between QinetiQ and <strong>Nimrod</strong> IPT representatives at Boscombe Down to<br />

monitor QinetiQ’s numerous on-going tasks for the <strong>Nimrod</strong> IPT.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!