in l<strong>and</strong>s having slopes less than 3 per cent.<br />

Originally. the project was c<strong>on</strong>ceived <strong>for</strong> irrigating paddy al<strong>on</strong>e but later.<br />

the scope <str<strong>on</strong>g>of</str<strong>on</strong>g> the scheme was extended to irrigate garden crops also in view <str<strong>on</strong>g>of</str<strong>on</strong>g> the<br />

change in the policy <str<strong>on</strong>g>of</str<strong>on</strong>g> the government. In additi<strong>on</strong> to this, it is anticipated that<br />

the scheme would solve drinking water problem to a c<strong>on</strong>siderable extent. The<br />

scheme is also expected to generate power to the extent <str<strong>on</strong>g>of</str<strong>on</strong>g> 15 MW. Besides,<br />

intensive agricultural activities are expected to create additi<strong>on</strong>al employment<br />

potential <str<strong>on</strong>g>of</str<strong>on</strong>g> 11.5 milli<strong>on</strong> m<strong>and</strong>ays.<br />

Eventhough scattered ef<strong>for</strong>ts have been <strong>on</strong> to investigate the possibilities<br />

<str<strong>on</strong>g>of</str<strong>on</strong>g> c<strong>on</strong>structing a dam across the river Kallada even be<strong>for</strong>e 1958. an oT(J.anised<br />

setup to investigate the possibility was started <strong>on</strong>ly in November 1958. The<br />

Government <str<strong>on</strong>g>of</str<strong>on</strong>g> Kerala in 1961 administratively sancti<strong>on</strong>ed the proposal <str<strong>on</strong>g>of</str<strong>on</strong>g><br />

KalLda Irrigati<strong>on</strong> project with an estimated cost <str<strong>on</strong>g>of</str<strong>on</strong>g> Rs. I 3 .28 crores. Thus the<br />

project was <strong>for</strong>mally started in 1961. The budget allotment <strong>for</strong> the project up to<br />

1966 was so meager that there were no tangible works carried out during the<br />

period. The expenditure up to 1980 March was <strong>on</strong>ly Rs.34 crores while the<br />

estimated cost at 1980 price levels was Rs. I 76 crores. The project was proposed<br />

to the World Bank aid in 1980 <strong>and</strong> the bank accepted the proposal in October<br />

1982 so as to complete the project hy March 1987. Later, it was extended up to<br />

March 1989. The World Bank aid n:ceived was 80.3 milli<strong>on</strong> US Dollars.<br />

equivalent to 97.77 crores <str<strong>on</strong>g>of</str<strong>on</strong>g> rupees (hased <strong>on</strong> the then exchange rate <str<strong>on</strong>g>of</str<strong>on</strong>g> Dollar).<br />

The spillover works were carried out thereafter utilising the budget allotment <str<strong>on</strong>g>of</str<strong>on</strong>g><br />

the state government. The partial commissi<strong>on</strong>ing <str<strong>on</strong>g>of</str<strong>on</strong>g> the Right Bank main canal<br />

114