3. Limit operations to the minimum amount of space needed to complete the specified<br />

Work.<br />

4. Maintain storm sewers and sanitary sewers in service at all times. Provide temporary<br />

service around the construction or otherwise construct the structure in a manner that<br />

the flow is not restricted.<br />

B. Provide a Plan of Action if facilities must be taken out of operation.<br />

1.13 FIELD MEASUREMENTS<br />

A. Perform complete field measurements for products required to fit existing conditions prior<br />

to purchasing products or beginning construction.<br />

B. Verify property lines, control lines, grades, and levels indicated on the Drawings.<br />

C. Verify pipe class, equipment capacities, existing electrical systems and power sources for<br />

existing conditions.<br />

D. Check Shop Drawings and indicate the actual dimensions available where products are to be<br />

installed.<br />

E. Include field measurements in record drawings as required in Section 01 31 13, Project<br />

Coordination.<br />

1.14 REFERENCE DATA AND CONTROL POINTS<br />

A. The Engineer will provide the following control points:<br />

1. Reference data provided on the contract drawings.<br />

B. Locate and protect control points prior to starting the Work and preserve permanent<br />

reference points during construction. Do not change or relocate points without prior<br />

approval of the Engineer. Notify CMAR/Engineer when the reference point is lost,<br />

destroyed, or requires relocation. Replace Project control points on the basis of the original<br />

survey.<br />

C. Provide complete engineering layout of the work needed for construction.<br />

1. Provide competent personnel. Provide equipment including accurate surveying<br />

instruments, stakes, platforms, tools, and materials.<br />

2. Provide surveying with accuracy meeting the requirements established for Category 5<br />

<strong>Construction</strong> Surveying as established in the Manual of Practice of Land Surveying in<br />

Texas published by the Texas Society of Professional Surveyors, latest revision.<br />

3. Record data and measurements per standards.<br />

1.15 DELIVERY AND STORAGE<br />

A. Deliver products and materials to the Site in time to prevent delays in construction.<br />

B. Deliver packaged products to Site in original undamaged containers with identifying labels<br />

attached. Open cartons as necessary to check for damage and to verify invoices. Reseal<br />

cartons and store properly until used. Leave products in packages or other containers until<br />

installed.<br />

C. Deliver products that are too large to fit through openings to the Site in advance of the time<br />

enclosing walls and roofs are erected. Set in place, raised above floor on cribs.<br />

Project Management and Coordination – <strong>Bid</strong> <strong>Package</strong> #8 01 31 00-6<br />

Colorado River Municipal Water District<br />

Ward County Water Supply Expansion Project – <strong>North</strong> <strong>Well</strong> <strong>Field</strong><br />

5/24/2012