Colorado River Municipal Water District<br />

Raw Water Supply <strong>Well</strong> Sites<br />

Ward County <strong>North</strong> <strong>Well</strong> <strong>Field</strong><br />

SECTION 11 97 00<br />

SUBMERSIBLE PUMPS AND INSTALLATION<br />

PART 1 GENERAL<br />

1.1 SUMMARY<br />

A. Section Includes:<br />

1. Installation of submersible pumping units, complete in place. Includes column<br />

pipe, column check valve, casing pipe spacers, surface plate, discharge head, and<br />

appurtenances.<br />

2. Pump procurement: per the contract specified in the Summary of Work. Includes<br />

pump, motor, power cable, startup services, testing (manufacturing and field),<br />

and appurtenances.<br />

B. Related Sections<br />

1. Division 01 - General Requirements<br />

2. Division 26 - Electrical<br />

3. Division 40 - Process Integration<br />

1.2 REFERENCES<br />

A. American Water Works Association (AWWA):<br />

1. AWWA A100 - Standard for Water <strong>Well</strong>s<br />

2. AWWA C654 - Disinfection of <strong>Well</strong>s<br />

B. Texas Administrative Code (TAC):<br />

1. Title 30, Part 1, Chapter 290 - Public Drinking Water<br />

1.3 SUBMITTALS<br />

A. Product Data:<br />

1. Column pipe: Submit manufacturer’s catalog information on pipe materials and<br />

fittings. Submit mill test certificates indicating physical and chemical analysis.<br />

2. Column check valve: Submit manufacturer’s catalog information with valve data<br />

and ratings for each service.<br />

3. Submit manufacturer’s catalog information for related products as specified in<br />

related sections.<br />

1.4 STARTUP AND DEMONSTRATION<br />

A. The Owner reserves the right to operate each submersible pumping unit, after installation,<br />

for a period of thirty (30) days before final acceptance. During such period, the<br />

Contractor, or his field service technician, shall make such adjustments as may be<br />

deemed necessary to improve the operating performance of the equipment.<br />

May 18, 2012<br />

Submersible Pumps and Installation<br />

Revision 0 11 97 00 - 1