GENERAL CONDITIONS<br />

ARTICLE 1 - DEFINITIONS AND TERMINOLOGY<br />

1.01 Defined Terms<br />

A. Wherever used in the Contract Documents and<br />

printed with initial or all capital letters, the terms listed<br />

below will have the meanings indicated which are<br />

applicable to both the singular and plural thereof.<br />

1. Addenda--Written or graphic instruments<br />

issued prior to the opening of <strong>Bid</strong>s which clarify,<br />

correct, or change the <strong>Bid</strong>ding Requirements or the<br />

Contract Documents.<br />

2. Agreement--The written instrument which is<br />

evidence of the agreement between OWNER and<br />

CONTRACTOR covering the Work.<br />

3. Application for Payment--The form acceptable<br />

to ENGINEER which is to be used by CONTRACTOR<br />

during the course of the Work in requesting progress or<br />

final payments and which is to be accompanied by such<br />

supporting documentation as is required by the Contract<br />

Documents.<br />

4. Asbestos--Any material that contains more than<br />

one percent asbestos and is friable or is releasing<br />

asbestos fibers into the air above current action levels<br />

established by the United States Occupational Safety<br />

and Health Administration.<br />

5. <strong>Bid</strong>--The offer or proposal of a bidder submitted<br />

on the prescribed form setting forth the prices for<br />

the Work to be performed.<br />

6. <strong>Bid</strong>ding Documents--The <strong>Bid</strong>ding<br />

Requirements and the proposed Contract Documents<br />

(including all Addenda issued prior to receipt of <strong>Bid</strong>s).<br />

7. <strong>Bid</strong>ding Requirements--The Advertisement or<br />

Invitation to <strong>Bid</strong>, Instructions to <strong>Bid</strong>ders, <strong>Bid</strong> security<br />

form, if any, and the <strong>Bid</strong> form with any supplements.<br />

8. Bonds--Performance and payment bonds and<br />

other instruments of security.<br />

9. Change Order--A document recommended by<br />

ENGINEER which is signed by CONTRACTOR and<br />

OWNER and authorizes an addition, deletion, or<br />

revision in the Work or an adjustment in the Contract<br />

Price or the Contract Times, issued on or after the<br />

Effective Date of the Agreement.<br />

10. Claim--A demand or assertion by OWNER or<br />

CONTRACTOR seeking an adjustment of Contract<br />

Price or Contract Times, or both, or other relief with<br />

respect to the terms of the Contract. A demand for<br />

money or services by a third party is not a Claim.<br />

11. Contract--The entire and integrated written<br />

agreement between the OWNER and CONTRACTOR<br />

concerning the Work. The Contract supersedes prior<br />

negotiations, representations, or agreements, whether<br />

written or oral.<br />

12. Contract Documents--The Contract Documents<br />

establish the rights and obligations of the parties and<br />

include the Agreement, Addenda (which pertain to the<br />

Contract Documents), CONTRACTOR’s <strong>Bid</strong> (including<br />

documentation accompanying the <strong>Bid</strong> and any post <strong>Bid</strong><br />

documentation submitted prior to the Notice of Award)<br />

when attached as an exhibit to the Agreement, the<br />

Notice to Proceed, the Bonds, these General Conditions,<br />

the Supplementary Conditions, the Specifications and<br />

the Drawings as the same are more specifically<br />

identified in the Agreement, together with all Written<br />

Amendments, Change Orders, Work Change Directives,<br />

<strong>Field</strong> Orders, and ENGINEER’s written interpretations<br />

and clarifications issued on or after the Effective Date<br />

of the Agreement. Approved Shop Drawings and the<br />

reports and drawings of subsurface and physical<br />

conditions are not Contract Documents. Only printed<br />

or hard copies of the items listed in this paragraph are<br />

Contract Documents. Files in electronic media format<br />

of text, data, graphics, and the like that may be<br />

furnished by OWNER to CONTRACTOR are not<br />

Contract Documents.<br />

13. Contract Price--The moneys payable by OWN-<br />

ER to CONTRACTOR for completion of the Work in<br />

accordance with the Contract Documents as stated in<br />

the Agreement (subject to the provisions of paragraph<br />

11.03 in the case of Unit Price Work).<br />

14. Contract Times--The number of days or the<br />

dates stated in the Agreement to: (i) achieve Substantial<br />

Completion; and (ii) complete the Work so that it is<br />

ready for final payment as evidenced by ENGINEER’s<br />

written recommendation of final payment.<br />

00700 - 6