2) Horizontal and vertical locations of underground utilities and appurtenances<br />

constructed and existing utilities encountered during construction.<br />

3) Location of internal utilities and appurtenances concealed in the construction.<br />

Refer measurements to permanent structure on the surface. Include the<br />

following equipment:<br />

a) Piping<br />

b) Ductwork<br />

c) Equipment and control devices requiring periodic maintenance or repair<br />

d) Valves, unions, traps, and tanks<br />

e) Services entrance<br />

f) Feeders<br />

g) Outlets<br />

4) Changes of dimension and detail<br />

5) Changes made by <strong>Field</strong> Order and Change Order<br />

6) Details not on the original Drawings. Include field verified dimensions and<br />

clarifications, interpretations, and additional information issued in response to<br />

RFI’s.<br />

c. Mark Specifications and Addenda to identify products provided.<br />

1) Record product name, trade name, catalog number, and each Supplier (with<br />

address and phone number) of each product and item of equipment actually<br />

installed.<br />

2) Record changes made by <strong>Field</strong> Order and Change Order.<br />

d. Mark additional Work or information in erasable pencil.<br />

1) Use red for new or revised indication.<br />

2) Use purple for Work deleted or not installed (lines to be removed).<br />

3) Highlight items constructed per the Contract Documents in yellow.<br />

e. Submit record documents to CMAR for review and acceptance 30 days prior to final<br />

completion of the project.<br />

1) Provide one (1) set of marked up drawings.<br />

2) Provide six (6) sets of specifications.<br />

D. Applications for Payment will not be recommended for payment if record documents are<br />

found to be incomplete or not in order. Final payment will not be recommended without<br />

complete record documents.<br />

1.10 REVIEW BY CMAR, ENGINEER AND OWNER<br />

A. The Owner and authorized representatives and agents of the Owner shall have access to<br />

and be permitted to observe and review all work, materials, equipment, payrolls, personnel<br />

records, employment conditions, material invoices, and other relevant data and records<br />

pertaining to this Contract at all times, provided, however that all instructions and approval<br />

with respect to the Work will be given to the <strong>Bid</strong>der only by the Owner through authorized<br />

representatives or agents.<br />

END OF SECTION<br />

Project Coordination – <strong>Bid</strong> <strong>Package</strong> #8 01 31 13-6<br />

Colorado River Municipal Water District<br />

Ward County Water Supply Expansion Project – <strong>North</strong> <strong>Well</strong> <strong>Field</strong><br />

5/24/2012

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!