10.07 Waiver of Claims<br />

A. The making and acceptance of final payment will constitute:<br />

1. a waiver of all Claims by Buyer against Seller, except Claims arising from unsettled liens<br />

from non-conformities in the Goods or Special Services appearing after final paym ent,<br />

from Seller's failure to comply with the Contract Documents or the terms of any s pecial<br />

guarantees specified therein, or from Seller's continuing obligations under the Contrac t<br />

Documents; and<br />

2. a waiver of all Claim s by Seller against Buyer (other than those previously m ade in<br />

accordance with the requirements herein and listed by Seller as unsettled as require d in<br />

Paragraph 10.05.A, and not resolved in writing).<br />

ARTICLE 11 – CANCELLATION, SUSPENSION, AND TERMINATION<br />

11.01 Cancellation<br />

A. Buyer has the right to cancel the Contract, without cause, at any time prior to delivery of the<br />

Goods by written notice. Cancellation pursuant to the terms of this paragraph shall not constitute<br />

a breach of contract by Buyer. Upon cancellation:<br />

1. Buyer shall pay Seller for the direct costs incurred in producing any Goods that Seller has<br />

specially manufactured for the Project, plus a fair and reasonable am ount for overhead<br />

and profit.<br />

2. For Goods that are not specially manufactured for the Project, Seller shall be entitled to a<br />

restocking charge of 10 percent of the unpaid Contract Price of such Goods.<br />

11.02 Suspension of Performance by Buyer<br />

A. Buyer has the right to suspend performance of the Contract for up to a maximum of ninety days,<br />

without cause, by written notice. Upon suspension under this paragraph, Seller shall be entitled<br />

to an increase in the Contract Times and Contract Price caused by the suspension, provided that<br />

performance would not have been suspended or delayed for causes attributable to Seller.<br />

11.03 Suspension of Performance by Seller<br />

A. Subject to the provisions of Paragraph 5.07.B, Seller may suspend the furnishing of the Goods<br />

and Special Services only under the following circumstance:<br />

1. Seller has reasonable grounds to conclude that Buyer will not perform its future payment<br />

obligations under the Contract; and,<br />

2. Seller has requested in writing assurances from Buyer that future payments will be made<br />

in accordance with the Contract, an d Buyer has failed to provide such assurances within<br />

ten days of Seller’s written request.<br />

EJCDC P-700, Standard General Conditions for Procurement Contracts.<br />

Copyright © 2010 National Society of Professional Engineers, American Council of Engineering Companies,<br />

American Society of Civil Engineers, and Associated General Contractors of America. All rights reserved.<br />