Colorado River Municipal Water District<br />

Raw Water Supply <strong>Well</strong> Sites<br />

Ward County <strong>North</strong> <strong>Well</strong> <strong>Field</strong><br />

1. Contractor shall verify that the well casing, screen, and sump are free of<br />

sediment. If sediment has accumulated, clean by bailing or other Engineerapproved<br />

method.<br />

2. Prior to installation of pumping equipment, Contractor to ensure pump outside<br />

diameter is at least one (1) inch less than the inside diameter of the well casing to<br />

the pump installation depth.<br />

D. Power cable: supported on the column pipe by means of cable clamps and stainless steel<br />

bands. Cable clamps shall be suitable for continuous submergence and carry an NSF seal<br />

if not stainless steel. Place cable clamps every 20 feet, minimum.<br />

E. Column check valves: Install less than 20 feet above the pump and thereafter in<br />

conformance with manufacturer suggested spacing. In no case shall the distance between<br />

valves and the surface plate be equal. Unequal distances are essential to prevent harmonic<br />

valve hammer.<br />

F. Surface plate: Install per manufacturer’s installation instructions and as indicated on the<br />

drawings.<br />

3.2 DISINFECTION<br />

A. Disinfection of <strong>Well</strong>s: per AWWA C654.<br />

B. The Contractor is advised that all wells were previously disinfected after construction and<br />

were found to be absent of coliform. Three consecutive days of testing were performed<br />

during the step-drawdown test. However, disinfection will be required following<br />

submersible pump installation.<br />

C. Contractor shall disinfect each well to satisfy the requirements of TCEQ Water Hygiene<br />

(Drinking Water) rules (TAC Chapter 290). Official testing for coliform will be<br />

conducted after the permanent pump has been installed. A minimum of 10 casing<br />

volumes shall have been evacuated prior to obtaining the official samples for testing.<br />

D. Forms of Chlorine: Disinfectant used for the wells shall be in liquid form. Solid tablets or<br />

powders will not be allowed. A simple chlorine solution will not be satisfactory.<br />

E. <strong>Well</strong> chlorination:<br />

1. Water in the well casing shall be treated with chlorine so that an average chlorine<br />

residual of 50 milligrams per liter (mg/L) is in the entire volume of water in the<br />

well casing. Chlorinated water shall rest in the well casing for at least 12 hours,<br />

but no more than 24 hours.<br />

2. Following the rest period, circulate the chlorinated water by pumping, wasting<br />

some of the water and returning some to the well, periodically testing for chlorine<br />

residual. When zero chlorine residual is measured, continue pumping the well to<br />

waste for at least 15 minutes or 10 casing diameters, whichever is greater. The<br />

Contractor shall then sample the well for bacteriological evaluation.<br />

3. Testing for chlorine residual shall be performed by the Contractor or his<br />

approved testing laboratory.<br />

May 18, 2012<br />

Submersible Pumps and Installation<br />

Revision 0 11 97 00 - 4