B. Provide labor, materials, tools, equipment, and related items for testing by the Owner, the<br />

CMAR, the Engineer or their Materials Testing laboratory including, but not limited to<br />

temporary construction required for testing and operation of new and existing utilities.<br />

Assist the Owner, CMAR, Engineer, and testing organizations in performing quality<br />

assurance activities.<br />

1. Provide access to the Work and to Subcontractor’s and Supplier's operations at all times<br />

Work is in progress.<br />

2. Cooperate fully in the performance of sampling, inspection, and testing.<br />

3. Furnish labor and facilities to:<br />

a. Provide access to the work to be tested.<br />

b. Obtain and handle samples for testing at the project site or at the source of the<br />

product to be tested.<br />

c. Facilitate inspections and tests.<br />

d. Provide adequate lighting to allow Owner observations.<br />

e. Store and cure test samples.<br />

4. Furnish copies of the tests performed on materials and products.<br />

5. Provide adequate quantities of representative product to be tested to the laboratory at<br />

the designated location.<br />

6. Give the CMAR/Engineer adequate notice before proceeding with work that would<br />

interfere with testing.<br />

7. Notify the CMAR/Engineer and the testing laboratory prior to the time that testing is<br />

required. Lead time is to be adequate to allow arrangements to be made for testing.<br />

8. Do not proceed with any work until testing services have been performed and results of<br />

tests indicate that the work is acceptable.<br />

9. Provide complete access to the Site and make Contract Documents available.<br />

10. Provide personnel and equipment needed to perform sampling or to assist in making<br />

the field tests.<br />

11. Quality assurance testing performed by the Owner will be paid for by the Owner, except<br />

for verification testing performed by the Owner, which shall be paid for by the <strong>Bid</strong>der as<br />

described in Paragraph 1.06.<br />

C. Quality assurance activities of the Owner, CMAR or Engineer through their own forces or<br />

through contracts with materials testing laboratories and survey crews are for the purpose<br />

of monitoring the results of the <strong>Bid</strong>der's work to see that it is in compliance with the<br />

requirements of the Contract Documents.<br />

D. <strong>Bid</strong>der may rely on the technical results of all tests provided, but interpretation of those test<br />

results will be provided by the CMAR/Engineer. Quality assurance activities of the Owner,<br />

CMAR and Engineer or non‐performance of quality assurance activities:<br />

1. Do not relieve the <strong>Bid</strong>der of its responsibility to perform Work and furnish materials and<br />

products and constructed Work conforming to the requirements of the Contract<br />

Documents.<br />

2. Do not relieve the <strong>Bid</strong>der of its responsibility for providing adequate quality control<br />

measures.<br />

3. Do not relieve the <strong>Bid</strong>der of responsibility for damage to or loss of the material, product<br />

or Work before Owner's acceptance.<br />

4. Do not constitute or imply Owner's acceptance.<br />

Quality Requirements – <strong>Bid</strong> <strong>Package</strong> #8 01 40 00‐2<br />

Colorado River Municipal Water District<br />

Ward County Water Supply Expansion Project – <strong>North</strong> <strong>Well</strong> <strong>Field</strong><br />

5/28/2012

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!