h. Energize switchgear. Measure and record instrument indications for no load and<br />

connected load conditions.<br />

G. Transformers<br />

1. Test single and three phase, liquid filled and dry transformers rated 5KVA and larger in<br />

accordance with the "Transformer Test Report," form.<br />

2. Record the following information and attach to the test report.<br />

a. Verify proper operation of all fans, alarms, and other auxiliary and monitoring<br />

devices.<br />

b. Verify "tap changer" operation, if applicable, in all positions. Set and secure "tap<br />

changer" to position recommended by the Engineer or Engineer.<br />

c. Obtain insulating liquid sample from all liquid filled transformers. Submit sample to<br />

testing laboratory, approved by the Owner for analysis. Perform standard insulating<br />

liquid tests as required by the Engineer or Engineer. Deliver test results to the<br />

Owner within 30 days after sampling.<br />

d. Perform insulation resistance tests at the test values shown below for the following<br />

equipment.<br />

e. Perform tests from each winding to ground and winding to winding. Primary and<br />

secondary sections shall be tested separately.<br />

f. Do not exceed the Supplier's recommended maximum test values or procedures.<br />

H. Motors<br />

Transformer Coil Rating<br />

Test Voltage<br />

0‐600 VOLTS 1,000 VOLTS<br />

601‐5,000 VOLTS 2,500VOLTS<br />

5,001‐15,000VOLTS<br />

5,000 VOLTS<br />

15,001‐39,000 VOLTS 10,000 VOLTS<br />

g. Provide additional tests and checks as recommended by the Supplier before<br />

energizing.<br />

h. Energize transformer. Measure and record primary and secondary volts and amps<br />

under no load and connected load conditions.<br />

1. Test electric motors in accordance with the "Motor Start‐Up Report" form.<br />

2. Check and record motor winding continuity phase to phase with a low voltage source.<br />

3. Check and record motor winding insulation resistance, each phase with respect to<br />

ground, at the test values shown below for A.C. induction motors per REF. IEEE Standard<br />

43.<br />

4. Do not exceed the Supplier's recommended maximum test values or procedures.<br />

Motor Voltage Rating (Volts)<br />

Test Voltage<br />

250V and below 500<br />

above 250 V 1,000<br />

2,360 Volt ‐ 3 Phase Per Manufacturer’s start‐up<br />

instructions or as otherwise directed<br />

by the Engineer.<br />

Quality Requirements – <strong>Bid</strong> <strong>Package</strong> #8 01 40 00‐15<br />

Colorado River Municipal Water District<br />

Ward County Water Supply Expansion Project – <strong>North</strong> <strong>Well</strong> <strong>Field</strong><br />

5/28/2012