C. Final Inspection:<br />

1. After all of the Goods have been incorporated into the Project, tested in accordan ce with<br />

such testing requirements as are sp ecified, and are functioning as indicated, Buyer or<br />

Engineer will make a final inspection.<br />

2. If, on the basis of the final inspection, the Goods are conforming, Buyer’s notice thereof<br />

will constitute Buyer’s acceptance of the Goods.<br />

3. If, on the basis of the final inspection, the Goods are non-conforming, Buyer will identify<br />

the non-conformity in writing.<br />

8.02 Non-Conforming Goods and Special Services<br />

A. If, on the basis of inspections and testing prior to delivery, the Goods and Special Services are<br />

found to be non-conforming, or if at any time after Buyer has acknowledged receipt of delivery<br />

and before the expiration of the correction period described in Paragraph 8.03, Buyer determines<br />

that the Goods and Special Services are non-conforming, then Seller shall promptly, without cost<br />

to Buyer and in response to written instructions from Buyer, either correct such non-conforming<br />

Goods and Special Services, or, if Goods are rejected by Buyer, remove and replace the nonconforming<br />

Goods with conforming Goods, including all work required for reinstallation.<br />

B. Buyer’s Rejection of Non-Conforming Goods:<br />

1. If Buyer elects to reje ct the Goods in whole or in pa rt, Buyer’s notice to Seller will<br />

describe in sufficient detail the non-confor ming aspect of the Goods. If Goods have been<br />

delivered to Buyer, Seller shall pro mptly, and within the Contract Tim es, remove and<br />

replace the rejected Goods.<br />

2. Seller shall bear all costs, losses and damages attributable to the removal and replacement<br />

of the non-conforming Goods as provided in Paragraph 8.02.E.<br />

3. Upon rejection of the Goods, Buye r retains a security interest in the Goods to the extent<br />

of any payments made and expenses incurred in their testing and inspection.<br />

C. Remedying Non-Conforming Goods and Special Services:<br />

1. If Buyer elects to permit the Seller to modify the Goods to correct the non-comfor mance,<br />

then Seller shall prom ptly provide a schedul e for such m odifications and shall make the<br />

Goods conforming within a reasonable time.<br />

2. If Buyer notifies Seller in writing that any of the Special Services are non-conforming,<br />

Seller shall promptly provide conforming services acceptable to Buyer. If Seller fails to<br />

do so, Buyer m ay delete the Special Serv ices and reduce the Contract Price a<br />

commensurate amount.<br />

EJCDC P-700, Standard General Conditions for Procurement Contracts.<br />

Copyright © 2010 National Society of Professional Engineers, American Council of Engineering Companies,<br />

American Society of Civil Engineers, and Associated General Contractors of America. All rights reserved.<br />