Colorado River Municipal Water District<br />

Raw Water Supply <strong>Well</strong> Sites<br />

Ward County <strong>North</strong> <strong>Well</strong> <strong>Field</strong><br />

3. Slope barbed wire arms outward.<br />

B. Maximum Spacing of Posts: 10-foot maximum spacing, uniform spacing or as shown on<br />

Drawings.<br />

C. Install line, corner and terminal posts plumb, set in concrete footings as specified in<br />

CLFMA standard.<br />

D. Set post to within 6 inches from bottom of concrete footing.<br />

E. Position bottom of fabric 2 inches above finished grade with tension wire stretched taut<br />

between posts.<br />

F. Pass top rail through line post tops to form continuous bracing.<br />

G. Install 7-inch-long couplings midspan at pipe ends.<br />

H. Bracing:<br />

1. Brace each gate and corner post back to adjacent line post with horizontal center<br />

brace rail.<br />

2. Install brace rail one bay from end and gate posts.<br />

3. Install center and bottom brace rail on corner and gate leaves<br />

I. Fasten fabric to top rail, line posts, braces and bottom tension wire with wire ties<br />

maximum 15-inch centers.<br />

J. Attach fabric to end, corner and gate posts with tension bars and tension bar clips.<br />

K. Stretch fabric between terminal posts or at intervals of 100 feet maximum, whichever is<br />

the least dimension.<br />

L. Install three strands of barbed wire on arms, tensioned and secured.<br />

M. Gates and Hinges:<br />

1. Install gates using fabric and barbed wire overhang to match fence.<br />

2. Install three hinges per leaf, latch, catches, drop bolt, retainer, and locking clamp.<br />

N. Provide concrete center rest and drop bolt retainers at center of double gate openings.<br />

3.2 SCHEDULE<br />

A. As shown on the Drawings.<br />

END OF SECTION<br />

May 18, 2012<br />

Chain Link Fences and Gates<br />

Revision 0 32 31 13 - 3