H. The CONTRACTOR shall expedite the repair or correction of any deficiency discovered<br />

during testing. The CONTRACTOR shall have personnel representing each trade to standby<br />

during the test period to immediately correct, repair, or adjust any item of hardware,<br />

software or field equipment causing a test to fail.<br />

I. The system shall operate continuously for 100 hours without failure before this test will be<br />

considered successful.<br />

3.09 30-DAY ACCEPTANCE TEST<br />

A. All database errors must be corrected prior to the start of the 30-Day Acceptance Test. The<br />

30-Day Acceptance Test will not be considered successful until all databases are correct.<br />

B. Any malfunction during the test shall be analyzed and corrections made by the Contractor.<br />

The Engineer and Owner will determine whether any such malfunctions are sufficiently<br />

serious to warrant a repeat of the test. The cost of a retest shall be borne by the<br />

CONTRACTOR as specified.<br />

C. After completion of the Functional Demonstration Test and Plant Start-up, the Contractor<br />

shall be responsible for operation of the entire System for a period of 30 consecutive days,<br />

under conditions of full plant process operation, without single non-field repairable<br />

malfunction.<br />

D. During this test, Contractor personnel shall be present as required. The Contractor shall<br />

provide personnel for this test who have an intimate knowledge of the hardware and<br />

software of the system and also are familiar with the overall plant process. The Supplier<br />

shall be on-site a minimum of 8 hours a day and be on call for the rest of the day, during the<br />

entire 30-Day Acceptance Test. During the rest of the test period the supplier shall be<br />

available and on the job site within 48 hours of any failure.<br />

E. While this test is proceeding, the Owner shall have full use of the system. Only plant<br />

operating personnel shall be allowed to operate equipment associated with live plant<br />

processes.<br />

F. Any malfunction, during this 30 consecutive day test period, which cannot be corrected<br />

within 24 hours of occurrence by the Contractor's personnel, or more than two similar<br />

failures of any duration, will be considered as a non-field-repairable malfunction.<br />

G. Upon completion of repairs, by the Supplier, the test shall be repeated as specified herein.<br />

H. In the event of rejection of any part or function, the Supplier shall perform repairs within 5<br />

days or replacement within 30 days.<br />

I. Upon successful completion of the 30-Day Acceptance Test, approval of all as-built drawing<br />

and O&M Manuals, completion of all related Owner training, and delivery of all spare,<br />

expendable, and test equipment, the systems shall be considered substantially complete<br />

and the warranty period shall commence.<br />

Supervisory Control and Data Acquisition (SCADA) System 40 90 02-34<br />

CMD11269 – Ward County Transmission System Expansion – Contract C – Above Slab TPS, OPS, and WPS