1.11 RESUBMISSION REQUIREMENTS<br />

A. Make all corrections or changes in the submittals required by the CMAR/Engineer and<br />

resubmit until approved.<br />

B. For Shop Drawings:<br />

1. Revise initial drawings or data and resubmit as specified for the original submittal.<br />

2. Highlight in yellow those revisions which have been made in response to the first review<br />

by the CMAR/Engineer.<br />

3. Highlight in blue any new revisions which have been made or additional details of<br />

information that has been added since the previous review by the CMAR/Engineer.<br />

C. For Samples:<br />

1. Submit new Samples as required for the initial Sample.<br />

2. Remove Samples which have been rejected.<br />

D. For mock-ups:<br />

1. Construct a new mock-up as initially required.<br />

2. Dispose of mock-ups which have been rejected.<br />

E. Pay for excessive review of Shop Drawings.<br />

1. Excessive review of Shop Drawings is defined as any review required after the original<br />

review has been made and the first resubmittal has been checked to see that<br />

corrections have been made.<br />

2. Cost for additional review time will be billed to the Owner by the Engineer for the actual<br />

hours required for the review and marking of shop drawings by Engineer and in<br />

accordance with the rates listed in Paragraph SC-14.02, Section 00 73 00,<br />

Supplementary Conditions<br />

3. Pay cost for the additional review to the Owner on a monthly basis as billed by the<br />

Owner.<br />

4. Need for more than one resubmission or any other delay of obtaining CMAR/Engineer's<br />

review of submittals, will not entitle the <strong>Bid</strong>der to an extension of Contract Time. All<br />

costs associated with such delays shall be at the <strong>Bid</strong>der's expense.<br />

1.12 ENGINEER'S DUTIES<br />

A. Review the submittals and return with reasonable promptness but not more than 21<br />

calendar days.<br />

B. Affix stamp, indicate approval, rejection, and the need for resubmittal.<br />

C. Distribute documents<br />

END OF SECTION<br />

Submittal Procedures – <strong>Bid</strong> <strong>Package</strong> #8 01 33 00-10<br />

Colorado River Municipal Water District<br />

Ward County Water Supply Expansion Project – <strong>North</strong> <strong>Well</strong> <strong>Field</strong><br />

5/24/2012

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!