1.05 FLOAT TIME<br />

A. Define float time as the amount of time between the earliest start date and the latest start<br />

date of a chain of activities on the construction schedule.<br />

B. Float time is not for the exclusive use or benefit of either the BIDDER, CMAR or Owner.<br />

C. Contract time cannot be changed by the submission of this schedule. Contract Time can<br />

only be modified by approved Change Order.<br />

D. Schedule completion date must be the same as the contract completion date. Time<br />

between the end of construction and the contract final completion date is to be indicated as<br />

float time.<br />

END OF SECTION<br />

<strong>Construction</strong> Process Schedule – <strong>Bid</strong> <strong>Package</strong> #8 01 32 16-3<br />

Colorado River Municipal Water District<br />

Ward County Water Supply Expansion Project – <strong>North</strong> <strong>Well</strong> <strong>Field</strong>s<br />