3.06 INITIAL MAINTENANCE<br />

A. Maintain equipment until the project is accepted by the Owner.<br />

1. Insure that mechanical equipment is properly greased, oiled, or otherwise cared for as<br />

recommended by the Supplier.<br />

2. Operate air handling equipment only when filters are in place and are clean. Change<br />

filters weekly during construction.<br />

B. Service equipment per the Supplier's instructions immediately before releasing the<br />

equipment to the Owner.<br />

1. Replace replaceable filters and clean permanent filters associated with air handling units<br />

or other packaged equipment.<br />

2. Remove and clean screens at strainers in piping systems.<br />

3. Clean insects from intake louver screens.<br />

END OF SECTION<br />

Starting and Adjusting – <strong>Bid</strong> <strong>Package</strong> #8 01 75 00-5<br />

Colorado River Municipal Water District<br />

Ward County Water Supply Expansion Project – <strong>North</strong> <strong>Well</strong> <strong>Field</strong><br />