maintaining and supervising of safety precautions and<br />

programs.<br />

6.15 Hazard Communication Programs<br />

A. CONTRACTOR shall be responsible for coordinating<br />

any exchange of material safety data sheets or other hazard<br />

communication information required to be made available to<br />

or exchanged between or among employers at the Site in<br />

accordance with Laws or Regulations.<br />

6.16 Emergencies<br />

A. In emergencies affecting the safety or protection of<br />

persons or the Work or property at the Site or adjacent<br />

thereto, CONTRACTOR is obligated to act to prevent<br />

threatened damage, injury, or loss. CONTRACTOR shall<br />

give ENGINEER prompt written notice if CONTRACTOR<br />

believes that any significant changes in the Work or<br />

variations from the Contract Documents have been caused<br />

thereby or are required as a result thereof. If ENGINEER<br />

determines that a change in the Contract Documents is<br />

required because of the action taken by CONTRACTOR in<br />

response to such an emergency, a Work Change Directive or<br />

Change Order will be issued.<br />

6.17 Shop Drawings and Samples<br />

A. CONTRACTOR shall submit Shop Drawings to<br />

ENGINEER for review and approval in accordance with the<br />

acceptable schedule of Shop Drawings and Sample<br />

submittals. All submittals will be identified as ENGINEER<br />

may require and in the number of copies specified in the<br />

General Requirements. The data shown on the Shop<br />

Drawings will be complete with respect to quantities, dimensions,<br />

specified performance and design criteria, materials,<br />

and similar data to show ENGINEER the services, materials,<br />

and equipment CONTRACTOR proposes to provide and to<br />

enable ENGINEER to review the information for the limited<br />

purposes required by paragraph 6.17.E.<br />

B. CONTRACTOR shall also submit Samples to<br />

ENGINEER for review and approval in accordance with the<br />

acceptable schedule of Shop Drawings and Sample<br />

submittals. Each Sample will be identified clearly as to<br />

material, Supplier, pertinent data such as catalog numbers,<br />

and the use for which intended and otherwise as ENGINEER<br />

may require to enable ENGINEER to review the submittal for<br />

the limited purposes required by paragraph 6.17.E. The<br />

numbers of each Sample to be submitted will be as specified<br />

in the Specifications.<br />

C. Where a Shop Drawing or Sample is required by the<br />

Contract Documents or the schedule of Shop Drawings and<br />

Sample submittals acceptable to ENGINEER as required by<br />

paragraph 2.07, any related Work performed prior to<br />

ENGINEER’s review and approval of the pertinent submittal<br />

will be at the sole expense and responsibility of<br />

CONTRACTOR.<br />

D. Submittal Procedures<br />

1. Before submitting each Shop Drawing or Sample,<br />

CONTRACTOR shall have determined and verified:<br />

a. all field measurements, quantities, dimensions,<br />

specified performance criteria, installation<br />

requirements, materials, catalog numbers, and similar<br />

information with respect thereto;<br />

b. all materials with respect to intended use,<br />

fabrication, shipping, handling, storage, assembly,<br />

and installation pertaining to the performance of the<br />

Work;<br />

c. all information relative to means, methods,<br />

techniques, sequences, and procedures of construction<br />

and safety precautions and programs incident thereto;<br />

and<br />

d. CONTRACTOR shall also have reviewed<br />

and coordinated each Shop Drawing or Sample with<br />

other Shop Drawings and Samples and with the<br />

requirements of the Work and the Contract Documents.<br />

2. Each submittal shall bear a stamp or specific<br />

written indication that CONTRACTOR has satisfied<br />

CONTRACTOR’s obligations under the Contract<br />

Documents with respect to CONTRACTOR’s review and<br />

approval of that submittal.<br />

3. At the time of each submittal, CONTRACTOR<br />

shall give ENGINEER specific written notice of such<br />

variations, if any, that the Shop Drawing or Sample<br />

submitted may have from the requirements of the Contract<br />

Documents, such notice to be in a written communication<br />

separate from the submittal; and, in addition, shall cause<br />

a specific notation to be made on each Shop Drawing and<br />

Sample submitted to ENGINEER for review and approval<br />

of each such variation.<br />

E. ENGINEER’s Review<br />

1. ENGINEER will timely review and approve Shop<br />

Drawings and Samples in accordance with the schedule of<br />

Shop Drawings and Sample submittals acceptable to<br />

ENGINEER. ENGINEER’s review and approval will be<br />

only to determine if the items covered by the submittals<br />

will, after installation or incorporation in the Work, conform<br />

to the information given in the Contract Documents<br />

00700 - 24