Colorado River Municipal Water District<br />

Vertical Turbine Submersible Pumping Units<br />

Ward County <strong>North</strong> <strong>Well</strong> <strong>Field</strong><br />

SECTION 01040<br />

COORDINATION AND MEETINGS<br />

PART 1 GENERAL<br />

1.1 Summary<br />

A. Section Includes<br />

1. Coordination.<br />

2. Meetings.<br />

3. Schedule of Work.<br />

1.2 Coordination<br />

A. Coordinate scheduling, submittals, and Work of the various sections of specifications to<br />

assure efficient and orderly sequence of installation of interdependent construction<br />

elements with provisions for accommodating items installed later.<br />

B. Verify that characteristics of equipment and materials to be incorporated into the project<br />

are compatible. Coordinate work of various sections having interdependent<br />

responsibilities for installing, connecting to, and placing in service, such equipment and<br />

materials.<br />

C. Installation contractor (to be determined and not a part of this Contract) will coordinate<br />

the schedule for installation of pumping equipment with the Seller.<br />

D. Coordinate delivery and storage of equipment with the Engineer and installation<br />

contractor.<br />

E. Coordinate startup with the Engineer and installation contractor.<br />

F. Coordinate field testing with the installation contractor.<br />

G. Prepare and document equipment installation report with the installation contractor.<br />

H. Complete and deliver operation and maintenance manuals following results of field<br />

testing.<br />

1.3 Meetings<br />

A. Participate in monthly progress meetings, as necessary, for other contracts associated<br />

with this project and relative to this Contract.<br />

1.4 Schedule of Work<br />

A. The Seller has full discretion in scheduling the Work.<br />

January 2012<br />

Coordination and Meetings<br />

Revision 0 01040 - 1