3.01 SERVICES OF SUPPLIER'S' REPRESENTATIVES<br />

A. The Supplier's representative for inspection, supervision of installation, and training must be<br />

an experienced and competent technical (not sales) representative of the manufacturer or<br />

Supplier.<br />

B. Perform installation, adjustment, and testing of the equipment under the direct supervision<br />

of the Supplier's representative where specified.<br />

C. The Supplier's representative is to instruct the Owner or his authorized personnel on<br />

operational procedures and maintenance requirements.<br />

D. Include the cost of the services of the Supplier's representative in the equipment price.<br />

3.02 INSPECTION AND START-UP<br />

A. Inspect equipment prior to placing any equipment or system into operation. Make<br />

adjustments as necessary for proper operation.<br />

1. Check for adequate and proper lubrication.<br />

2. Determine that parts or components are free from undue stress from structural<br />

members, piping or anchorage.<br />

3. Adjust equipment for proper balance and operations.<br />

4. Determine that vibrations are within acceptable limits.<br />

5. Determine that equipment operates properly under full load conditions.<br />

6. Determine that the equipment is in true alignment.<br />

B. Have the Supplier's representative present when the equipment is placed in operation.<br />

1. The Representative is to be on site as often as necessary for proper and trouble free<br />

operation.<br />

2. Ensure that the proper procedure is employed in start up of systems.<br />

C. Provide Equipment Installation Reports for Equipment on the form indicated by Engineer.<br />

1. Certify that the equipment and related appurtenances have been thoroughly examined<br />

and approved for start-up and operation.<br />

2. Include the date when Owner's personnel were instructed in the proper operation and<br />

maintenance of the equipment in the report.<br />

3.03 STARTING REQUIREMENTS<br />

Refer to the individual sections of the specifications for specific start up procedures.<br />

3.04 INITIAL OPERATION<br />

A. Start, test, and place equipment and systems into operation for 30 days to allow the Owner,<br />

CMAR and Engineer to observe the operation and overall performance of the equipment<br />

and to determine that controls function as intended.<br />

B. Equipment which operates on a limited or part-time basis shall be operated in the presence<br />

of the CMAR and Engineer to demonstrate that controls function as specified.<br />

C. Perform acceptance test as specified in individual specification sections. Demonstrate that<br />

equipment and systems meet the specified performance criteria.<br />

Starting and Adjusting – <strong>Bid</strong> <strong>Package</strong> #8 01 75 00-2<br />

Colorado River Municipal Water District<br />

Ward County Water Supply Expansion Project – <strong>North</strong> <strong>Well</strong> <strong>Field</strong><br />