Colorado River Municipal Water District<br />

Raw Water Supply <strong>Well</strong> Sites<br />

Ward County <strong>North</strong> <strong>Well</strong> <strong>Field</strong><br />

SECTION 26 01 26<br />

TESTING OF ELECTRICAL SYSTEMS<br />

PART 1 GENERAL<br />

1.1 WORK INCLUDED<br />

A. Furnish labor, material, equipment and incidentals of a NETA certified independent<br />

testing agency. Testing shall be inclusive of all low voltage equipment including<br />

conductors for the pump station. Testing shall include all relay protective schemes and<br />

operation of the medium and low voltage equipment.<br />

1.2 QUALITY ASSURANCE<br />

A. Independent testing agency shall be NETA certified.<br />

1.3 SUBMITTALS<br />

Submittals shall be in accordance with Section 01 33 00, “Submittal Procedures” and shall<br />

include:<br />

A. ELECTRICAL TESTING REPORT<br />

1. 60 days prior to any testing taking place, Contractor shall submit to the<br />

Owner/Engineer the name of the testing agency; a list of all tests to be conducted<br />

shall also be submitted at this same time.<br />

2. A written report shall be submitted by the testing agency performing installation<br />

checks, operation and testing of the low voltage equipment. This report shall<br />

certify that 1) the equipment has been properly installed, 2) is in accurate<br />

alignment, 3) meets the acceptance testing specifications of NETA and the<br />

equipment manufacturer, and 4) NETA certification of the testing agency.<br />

Provide a detailed list of all tests that were performed and the test results as part of<br />

the Electrical Testing Report.<br />

3. Electrical Testing Report shall be submitted to the Engineer for approval at least 4<br />

weeks before start-up.<br />

1.4 STANDARDS<br />

A. The applicable provisions of the following standards shall apply as if written here in their<br />

entirety:<br />

1. American National Standards Institute (ANSI)<br />

2. American Standards for Testing and Materials (ASTM)<br />

3. Institute of Electrical and Electronic Engineers (IEEE)<br />

4. National Electrical Manufacturers Association (NEMA)<br />

5. International Electrical Testing Association (NETA)<br />

May 18, 2012<br />

Testing of Electrical Systems<br />

Revision 0 26 01 26-1