4,160 Volt ‐ 3 Phase Per Manufacturer’s start‐up<br />

instructions or as otherwise directed<br />

by the Engineer.<br />

5. Check and record motor circuit voltage before starting motor.<br />

6. Verify operation of motor space heater if applicable.<br />

7. Provide additional tests and checks as recommended by the Supplier before energizing.<br />

8. Start motor and verify immediately correct shaft rotation.<br />

9. Check and record motor running volts and amps.<br />

10. Verify correct operation of all interlocking and protective devices.<br />

4.00 SUBMERSIBLE PUMPS<br />

4.01 SUMMARY<br />

A. Section Includes<br />

1. Quality control and control of installation.<br />

2. Tolerances.<br />

3. References.<br />

4. Labeling.<br />

5. Testing and inspection services.<br />

6. Electrical Testing<br />

7. Manufacturers' field services.<br />

8. Examination.<br />

9. Preparation.<br />

4.02 QUALITY CONTROL AND CONTROL OF INSTALLATION<br />

A. Monitor quality control over suppliers, manufacturers, products, services, site conditions,<br />

and workmanship, to produce Work of specified quality.<br />

B. Comply with manufacturers' instructions, including each step in sequence.<br />

C. When manufacturers' instructions conflict with Contract Documents, request clarification<br />

from Engineer before proceeding.<br />

D. Comply with specified standards as minimum quality for the Work except where more<br />

stringent tolerances, codes, or specified requirements indicate higher standards or more<br />

precise workmanship.<br />

E. Perform Work by persons qualified to produce required and specified quality.<br />

F. Verify field measurements are as indicated on Shop Drawings or as instructed by<br />

manufacturer.<br />

G. Secure products in place with positive anchorage devices designed and sized to withstand<br />

stresses, vibration, physical distortion, or disfigurement.<br />

Quality Requirements – <strong>Bid</strong> <strong>Package</strong> #8 01 40 00‐16<br />

Colorado River Municipal Water District<br />

Ward County Water Supply Expansion Project – <strong>North</strong> <strong>Well</strong> <strong>Field</strong><br />

5/28/2012

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!