6. Successor and predecessor relationships for each activity. Group related activities or<br />

use lines to indicate relationships.<br />

7. A clearly indicated critical path. Indicate only one critical path on the schedule. The<br />

subsystem with the longest time of completion is the critical path where several<br />

subsystems each have a critical path. Float time is to be assigned to other subsystems.<br />

8. Projected percentage of completion, based on dollar value of the Work included in each<br />

activity to the last day of the pay period for each Applications for Payment.<br />

C. Submit a separate submittal schedule indicating the dates when the submittals are to be<br />

sent to the CMAR/Engineer.<br />

1. List specific dates submittal is to be sent to the CMAR/Engineer.<br />

2. List specific dates submittal must be processed in order to meet the proposed schedule.<br />

3. Allow a reasonable time to review submittals, taking into consideration the size and<br />

complexity of the submittal, the submission of other submittals, and other factors that<br />

may affect review time.<br />

4. Allow time for re-submission of the submittals for each item. BIDDER is responsible for<br />

delays associated with additional time required to review incomplete or erroneous<br />

submittals and for the time lost when submittals are submitted for products that do not<br />

meet specification requirements.<br />

D. Update the schedule at the end of each monthly partial payment period to indicate the<br />

progress made on the project to that date.<br />

1.04 SCHEDULE REVISIONS<br />

A. Submit a written report if the schedule indicates that the Project is more than thirty days<br />

behind schedule. The report is to include:<br />

1. Number of days Project is behind schedule.<br />

2. Narrative description of the steps to be taken to bring the Project back on schedule.<br />

3. Anticipated time required to bring the Project back on schedule.<br />

Submit a revised schedule indicating the action that the BIDDER proposes to take to bring<br />

the Project back on schedule.<br />

B. Revise the schedule to indicate any adjustments in Contract Time approved by Change<br />

Order.<br />

1. Revised schedule is to be included with Contract Modification Request for which an<br />

extension of time is requested.<br />

2. Failure to submit a revised schedule indicates that the modification shall have no impact<br />

on the ability of the BIDDER to complete the project on time and that the cost<br />

associated with the change of additional plant or work force have been included in the<br />

cost proposed for the modification.<br />

C. Updating the project schedule to reflect actual progress is not considered a revision to the<br />

project schedule.<br />

D. Applications for Payment will not be recommended for payment without a revised schedule<br />

and if required, the report indicating the BIDDER's plan for bringing the project back on<br />

schedule.<br />

<strong>Construction</strong> Process Schedule – <strong>Bid</strong> <strong>Package</strong> #8 01 32 16-2<br />

Colorado River Municipal Water District<br />

Ward County Water Supply Expansion Project – <strong>North</strong> <strong>Well</strong> <strong>Field</strong>s<br />

5/24/2012