a. Perform insulation resistance test on 5KV cable for insulation resistance tested at<br />

2,500 volts with respect to ground and at 2,500 volts with respect to all other<br />

conductors in each circuit.<br />

b. H‐Pot test 5KV cables incrementally to 25 KVDC for 15 minutes per ANSI/IEE STD<br />

400. Record leakage current in the spaces provided, at the time intervals shown, on<br />

the "Medium Voltage Cable Test Report." Do not exceed the cable Supplier’s<br />

maximum test values or procedures.<br />

c. Perform Individual conductor resistance tests and recorded results. Test each<br />

circuit for continuity between terminations ends and record the test results.<br />

Provide additional tests and checks as requested by the Supplier.<br />

4. 15kv Cable And Conductors:<br />

a. Perform insulation resistance test on 15KV cable at 2500 volts with respect to all<br />

other conductors in each circuit.<br />

b. H‐Pot test 15KV cable incrementally to 55KVDC for 15 minutes per ANSI/IEE STD.<br />

400. Record leakage current at the time interval, shown, on the "Medium Voltage<br />

Cable Test Report." Do not exceed the cable Supplier's recommended maximum<br />

test values or procedures. Perform individual conductor resistance tests and record<br />

the results. Test each circuit for continuity between terminating ends and record<br />

the results. Provide additional tests and checks as required by the Supplier.<br />

F. Switchgear<br />

1. Test electrical switchgear and electrical devices and controls mounted on or in the<br />

switchgear in accordance with the "Switchgear Test Report" form.<br />

2. Record the following information and attach to the test report:<br />

a. Resistance reading across joints of each horizontal and vertical bus.<br />

b. Verify proper operation of electrical, mechanical and keyed interlocking systems.<br />

c. Operate devices at both their open and closed states. Operate stored energy<br />

devices mechanically and electrically as applicable. Operate remotely controlled<br />

devices from their remote location.<br />

d. Verify proper operation of draw‐out circuit breakers and switches. Remove and reinstall<br />

each unit. Verify proper operation of shutters and barriers.<br />

e. Disconnect electrical and electronic sensing and protective devices not rated to<br />

withstand insulation resistance test potentials. Reconnect the devices before<br />

energizing the switchgear.<br />

f. Perform insulation resistance tests at the test voltages shown below for the<br />

following equipment. Do not exceed the Supplier's recommended maximum test<br />

values or procedures.<br />

Equipment Rating<br />

Test Voltage<br />

0‐250 VOLTS 500 VOLTS<br />

251‐600 VOLTS 1,000 VOLTS<br />

601‐5,000 VOLTS 2,500 VOLTS<br />

5,001‐15,000 VOLTS 2,500 VOLTS<br />

15,001‐39,000 VOLTS 5,000 VOLTS<br />

g. Provide additional tests and checks as recommended by the Supplier before<br />

energizing.<br />

Quality Requirements – <strong>Bid</strong> <strong>Package</strong> #8 01 40 00‐14<br />

Colorado River Municipal Water District<br />

Ward County Water Supply Expansion Project – <strong>North</strong> <strong>Well</strong> <strong>Field</strong><br />

5/28/2012

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!