Colorado River Municipal Water District<br />

Raw Water Supply <strong>Well</strong> Sites<br />

Ward County <strong>North</strong> <strong>Well</strong> <strong>Field</strong><br />

2.3 JOINT MATERIALS<br />

A. Waterstops: flat dumbbell type not less than 3 / 16 -inch for widths up to 5-inches and made<br />

of rubber in accordance with ASTM D1752 or preformed polychloroprene elastomeric<br />

joint seals in accordance with ASTM D2628.<br />

B. Expansion joints: not less than ½-inch and placed between new and existing concrete slab<br />

construction.<br />

1. Provided by placing asphalt, coal-tar saturated felt, or equivalent material in<br />

accordance with ASTM D994.<br />

2. Continuously sealed utilizing a sealant approved by the manufacturer of the<br />

expansion joint materials.<br />

2.4 CONCRETE MIX<br />

A. Mix and deliver concrete in accordance with ASTM C94, Alternative No. 2 and 3.<br />

B. Select proportions for normal weight concrete in accordance with ACI 301 Method 1,<br />

Method 2 and Method 3.<br />

C. Provide concrete to the following criteria:<br />

1. Compressive Strength (28 days): 3,000 psi.<br />

2. Slump: 3 to 5 inches.<br />

3. Air: 4.5 to 7.5 percent.<br />

4. Water to cement ratio: 0.50.<br />

D. Use set retarding admixtures during hot weather only when approved by Engineer.<br />

E. Add air entraining agent to normal weight concrete mix.<br />

PART 3 EXECUTION<br />

3.1 EXAMINATION<br />

A. Verify requirements for concrete cover over reinforcement.<br />

B. Verify that anchors, seats, plates, reinforcement and other items to be cast into concrete<br />

are accurately placed, positioned securely, and will not cause hardship in placing<br />

concrete.<br />

3.2 PREPARATION<br />

A. Prepare previously placed concrete by cleaning with steel brush and applying bonding<br />

agent in accordance with manufacturer's instructions.<br />

3.3 PLACING CONCRETE<br />

A. Place concrete in accordance with ACI 304.<br />

May 18, 2012<br />

Cast-in-Place Concrete<br />

Revision 0 03 30 00 - 3