22.01.2014 Views

Azura-Edo Independent Power Plant Environmental Impact ... - IFC

Azura-Edo Independent Power Plant Environmental Impact ... - IFC

Azura-Edo Independent Power Plant Environmental Impact ... - IFC

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Type of Emission<br />

Solid waste<br />

All solid wastes generated during construction (surplus spoil) and<br />

operation (waste chemicals, office waste and small amounts of<br />

hazardous waste) will be disposed of at an appropriately licensed<br />

landfill site. <strong>Azura</strong> <strong>Power</strong> will identify appropriate landfill sites<br />

during the detailed design phase.<br />

Project Schedule<br />

It is estimated that the facility will be operational by second quarter of 2015. Site<br />

preparation and construction is expected begin in the fourth quarter of 2012 and<br />

to be completed by the fourth quarter of 2014. Testing and commissioning is<br />

expected to be undertaken between the fourth quarter of 2014 and be completed<br />

by the first quarter of 2015. The lifetime of the Project is expected to be 20 years<br />

and decommissioning to take place from 2035.<br />

Project Activities<br />

Construction Phase<br />

Project activities will commence with site clearance of vegetation, earthworks,<br />

site levelling and construction of site roads. The “lay down” area will be on the<br />

area reserved for the Heat Recovery Steam Generators (HRSGs) and steam<br />

turbines. A temporary construction camp will be established to house the<br />

employees during the construction phase within the site (on the western portion)<br />

and will include (to be confirmed on appointment of EPC contractor) housing,<br />

kitchens, eating areas and latrines. Site preparation will involve vegetation<br />

clearing activities and removal of organic material, removal of unsuitable<br />

material and top soil, and levelling and compaction, including cut to fill, and<br />

borrowing to fill from an approved source of material.<br />

Screw piling (auger piling) of the foundations for the gas turbines and other<br />

large items of equipment will commence six months into the construction<br />

schedule, and will last for three to four months. Once the piles are in place,<br />

concrete slabs and turbine pedestals will be formed using large concrete pours.<br />

The gas turbine building and overhead 330 kV cables will be constructed at<br />

around 15 months while gas turbines and other heavy equipment will be<br />

delivered at 12 - 18 months, associated with abnormal loads on the roads. Raw<br />

materials will be sourced locally to the extent possible.<br />

Construction will generally be during daylight hours, however the final stages of<br />

installation and commissioning may proceed 24 hours a day, seven days a week<br />

Approximately 500 people will be employed during the construction phase and<br />

up to 70 percent of the construction workers can be sourced locally, from within<br />

30 km of the Site.<br />

AZURA EDO IPP<br />

XI<br />

DRAFT EIA REPORT

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!