construction noise associated with the NIPP project. From review of the NIPP<br />

ESI Report, the average overall noise levels measured as part of their baseline<br />

studies were recorded at 34 dB (A) (wet season) and 37 dB (A) (dry season).<br />

As with standard methodology, and based on this, the baseline noise levels<br />

are therefore considered to be below the <strong>IFC</strong> Noise Level Guidelines for<br />

daytime, 55 dB(A) LAeq, 15hr, and 45 dB(A) LAeq, 9hr, for night time for<br />

residential, institutional or educational receptors.<br />

7.4.2 Noise Receptors<br />

The noise sensitive receptors close to the site and considered in the impact<br />

assessment include a number of occupied and unoccupied houses, farms and<br />

community infrastructure such as churches and sacred sites within the three<br />

communities of Orior-Osemwende, Ihovbor-Eveboeka and<br />

Idunmwumowinna-Uhro-Nisen.<br />

There are twenty-four occupied houses within the community of Orior-<br />

Osemwende and four farms. Within Ihovbor-Eveboeka, there are twenty<br />

occupied farms, one unoccupied house and five receptors consisting of<br />

community-related infrastructure (churches or graves). In addition, within<br />

the community of Idunmwumowinna-Uhro-Nisen, there are twenty-two<br />

occupied houses and one unoccupied house (lying approximately 1 km to the<br />

west of the site and therefore not shown on the map).<br />

7.4.3 <strong>Impact</strong> Description and Significance: Construction<br />

<strong>Impact</strong> Description<br />

With regard to noise emissions, there are no specific positive impacts relating<br />

to the construction of the proposed project.<br />

Construction of the plant will take up to two years, and will include<br />

approximately two months of earthworks and site clearance, the preparation<br />

of footings for the plant, heavy earthworks and the construction and<br />

installation of the superstructures.<br />

Proposed construction hours are 0700 – 1800 Monday to Saturday. Auger<br />

(“screw”) piling will take place; but no impact piling is anticipated and as<br />

such, vibration impacts are not considered likely given the distance between<br />

the site and the closest sensitive properties. Noise from construction activities<br />

are likely to be perceptible at the closest noise sensitive properties during the<br />

key phases of the work, particularly earthworks and any activities where a<br />

number of items of plant will be operating simultaneously.<br />

<strong>Impact</strong> Significance<br />

In the absence of specific details on the proposed construction work<br />

programme and method, it is not possible to quantify construction noise<br />

AZURA EDO IPP<br />

7-32<br />

DRAFT EIA REPORT