Figure 6.6<br />

Consultation with the <strong>Edo</strong> State Public Private Partnership<br />

6.4.3 Stage 2A: EIA Study - Training and Capacity Building for RAP<br />

A training workshop was organised by ERM for EIA sub-consultants and the<br />

local Government authorities during the EIA and RAP Phase (documentation<br />

is included in Annex A). The brief workshop aimed to:<br />

• Discuss Project risks and the importance of stakeholder engagement as<br />

well as key ‘dos and don’ts’ of stakeholder engagement;<br />

• Outline and explain the need for resettlement and a RAP;<br />

• Define and provide an understanding of resettlement and key<br />

resettlement terms, including an overview of WB OP 4.12 and key<br />

resettlement principles;<br />

• Provide an overview of the resettlement process and an understanding of<br />

the processes involved in a RAP;<br />

• Carry out a comparative analysis and gap assessment between the RAP<br />

process followed by the Government and that set out by the WB OP 4.12;<br />

and<br />

• Facilitate an understanding of eligibility and entitlement for a RAP.<br />

AZURA EDO IPP<br />

6-8<br />

DRAFT EIA REPORT