Ref<br />

#<br />

Potential<br />

impact<br />

Desired<br />

Outcome<br />

Description of mitigation<br />

• Use most effective mufflers, enclosures and low-noise tool<br />

bits and blades;<br />

• Investigate use of alternatives to audible reversing alarms<br />

(such as broadband noise emitting models) or configure to<br />

maximise forward movements of mobile plant;<br />

• Use alternatives to diesel/petrol engines and pneumatic<br />

units, such as hydraulic or electric-controlled units, where<br />

feasible and reasonable;<br />

• Use temporary noise barriers for small equipment, where<br />

required;<br />

• Reduce throttle settings and turn off equipment and plant<br />

when not used; and<br />

• Regular inspection and maintenance of all plant and<br />

equipment; and<br />

• Perform ongoing monitoring of noise levels at the four<br />

farm receptors (see Chapter 9) and submit results to<br />

FMEnv.<br />

Performance<br />

Indicator<br />

Monitoring<br />

Timing/<br />

Frequency<br />

Responsibility Estimated<br />

Cost (USD)<br />

2.3 Terrestrial Soils<br />

and Geology<br />

• Removal of<br />

soils and<br />

earthworks<br />

• Soil<br />

compaction<br />

• Increased<br />

erosion and<br />

sedimentatio<br />

n of water<br />

resources<br />

• Potential<br />

contaminatio<br />

n from spills<br />

Minimise soil<br />

loss, reduce<br />

erosion and<br />

decrease, risk<br />

of siltation of<br />

water<br />

resources<br />

and risk of<br />

contaminatio<br />

n<br />

• Effective site drainage including cut-off drains to divert<br />

surface runoff from exposed soils or construction areas;<br />

• Construct temporary drainage channels to channel and<br />

divert surface water away from any down slope land and<br />

agricultural plots;<br />

• Install oil/ water separators and silt traps before effluent<br />

leaves the site;<br />

• Implement low impact excavation, in-fill and trenching<br />

methods;<br />

• Minimise bare ground and stockpiles to avoid silt runoff;<br />

• Rehabilitate and revegetate cleared areas before the next<br />

wet season;<br />

• Bunding of areas where hazardous substances are stored<br />

(eg fuel, waste areas); and<br />

• Develop and implement of a waste management plan (as<br />

part of the ESMP).<br />

Visual<br />

inspection<br />

Visual<br />

inspection<br />

and<br />

photographic<br />

record<br />

Daily<br />

HSE<br />

Coordinator,<br />

<strong>Azura</strong> <strong>Power</strong><br />

Part of HSE<br />

Coordinator’<br />

s duties<br />

2.4 Water Resource<br />

impacts:<br />

• Potential<br />

Prevent<br />

contaminatio<br />

n of water<br />

• Placement soil stock piles to reduce exposure to wind or<br />

water;<br />

• Reduce or prevent off-site sediment transport using<br />

Effluent<br />

quality<br />

meeting<br />

Water quality<br />

monitoring<br />

before<br />

Every<br />

three<br />

months<br />

HSE<br />

Coordinator,<br />

<strong>Azura</strong> <strong>Power</strong><br />

Cost for<br />

sampling and<br />

analysis of