3.4 PROJECT SCHEDULE<br />

3.4.1 Overview<br />

Construction activities will involve site preparation activities and construction<br />

of the Project infrastructure, the power plant and the transmission line. Site<br />

roads will also be constructed at this stage to assist the movement of heavy<br />

equipment. A temporary construction camp will be built adjacent to the<br />

power plant site.<br />

During operation, the power plant will be operated on a 24 hour, seven days a<br />

week basis. The number of workers on site during commercial operations will<br />

be around 50 permanent site employees and a smaller number of ancillary and<br />

contract workers (including security, cleaning and gardening etc).<br />

A provisional schedule for Project Activities is outlined in Table 3.4. The<br />

facility is planned to be operational in the second quarter of 2015.<br />

Table 3.4<br />

Proposed Project Schedule<br />

Activity<br />

Approximate Date<br />

EPC Contractor Negotiations Q2 and Q3 2012<br />

Site preparation Q4 2012<br />

Construction period Q4 2012 – Q4 2014<br />

Testing and Commissioning Q4 2012 – Q1 2015<br />

Operation Q2 2015<br />

Decommissioning 2035<br />

Please note: This schedule is approximate and is based on information and planning available at<br />

the compilation of the EIA Report<br />

3.5 CONSTRUCTION AND COMMISSIONING<br />

3.5.1 Appointment of EPC Contractor<br />

The selected EPC Contractor will be responsible for designing the plant on a<br />

turnkey basis. The selected EPC Contractor will need to demonstrate that it<br />

has successfully designed and completed a number of similar plants. <strong>Azura</strong><br />

<strong>Power</strong> will use an experienced power plant consulting engineer to assist in the<br />

EPC contractor appointment process.<br />

The EPC contract will be either a single large “turnkey” agreement (<strong>Azura</strong><br />

<strong>Power</strong>’s preferred option) or a series of smaller EPC contracts with a<br />

management contract to hold these separate contracts together. <strong>Azura</strong> <strong>Power</strong><br />

has commenced the process of prequalification of potential EPC contractors.<br />

3.5.2 Overview of Activities and Schedule<br />

The initial stage of construction will involve site clearance of vegetation and<br />

earthworks and levelling of the Site. Site roads will be constructed at this<br />

stage to allow for the movement of heavy plant during the construction phase.<br />

The “lay down” area for the construction of the OCGT power plant will be on<br />