Gas Turbine Building<br />

The four gas turbines will be arranged in a line within the gas turbine<br />

building. A turbine crane will run the length of the building, with main access<br />

doors for maintenance from each end of the gas turbine building. An access<br />

corridor will run through the building along one side of the gas turbine units<br />

and a low level electrical annex will be situated close to the transformer and<br />

below the level of the gas turbine air intake filter housings.<br />

The electrical annex will house the switchgear, control cubicles and cabling for<br />

the gas turbine units and their auxiliaries. Diverter or damper units with<br />

bypass stacks will be included in each gas turbine exhaust to allow for future<br />

conversion to a CCGT plant. The gas turbines will be installed in a noise<br />

reducing enclosure to keep the noise levels from the gas turbines below 85<br />

dBA.<br />

Gas Turbines<br />

The initial design assumes a General Electric Frame 9E machine, but the<br />

chosen gas turbine may be a different E class gas turbine from an alternative<br />

manufacturer. It is estimated that the year of manufacture will be 2012 or later<br />

and that the Warranty will be for at least two years. These turbines have the<br />

following characteristics:<br />

• Maximum turbine capacity of 112.5 MW (140.625 MVA) and minimum<br />

turbine capacity of 67.5 MW (minimum turndown of 60 percent).<br />

• New and clean Heat Rate of 11,100 Btu/kWh (lower heating value) at the<br />

Project site conditions; new and clean efficiency of 32 percent.<br />

• The gas turbines will be fuelled by natural gas.<br />

• The gas turbine pressure ratio will be 12.6:1.<br />

• The gas turbines will be built in a noise reducing enclosure. The target<br />

noise outside of the enclosure will be less than 85 dBA (see Section 3.2.12).<br />

• The run-up and run-down rates will be 10 MW per minute for each unit or<br />

higher if more than one machine is running up or running down at any<br />

one time.<br />

• The Piezo ignition system or an equivalent electrical gas ignition system<br />

will be used.<br />

• Standard gas turbine accessories, including oil pumps, water pumps, fin<br />

fan coolers, electrical equipment and controls etc.<br />

• The air intake system consisting of a bag filter.<br />

AZURA EDO IPP<br />

3-6<br />

DRAFT EIA REPORT