22.01.2014 Views

Azura-Edo Independent Power Plant Environmental Impact ... - IFC

Azura-Edo Independent Power Plant Environmental Impact ... - IFC

Azura-Edo Independent Power Plant Environmental Impact ... - IFC

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

the area reserved for the HRSG and steam turbines which can later form part<br />

of the CCGT power station (Figure 3.1).<br />

Construction is expected to start in the fourth quarter of 2012 as indicated in<br />

Table 3.4. Construction activities will generally be restricted to daylight hours,<br />

however the final stages of installation and commissioning may proceed 24<br />

hours a day, seven days a week.<br />

Screw piling (auger piling) of the foundations for the gas turbines and other<br />

large items of equipment will commence six months into the construction<br />

schedule, and will last for three to four months. Once the piles are in place,<br />

concrete slabs will be constructed and turbine pedestals constructed which<br />

will involve some large pours of concrete. At this stage the gas turbine<br />

building will be constructed which will be the first visible impact of the power<br />

plant. The construction of the overhead 330 kV cables, which will evacuate<br />

power from the power plant and onto the national grid, will commence soon<br />

after financial close and will connect the power plant to the national grid at<br />

around 15 months.<br />

The gas turbines and other heavy equipment will be delivered in the period<br />

from 12 to 18 months which will involve some abnormal loads being moved<br />

on the roads during this period.<br />

After around 18 months general site activity will decrease as the project moves<br />

into commissioning where there will be a relatively small group of highly<br />

skilled engineers and technicians commissioning the power plant.<br />

3.5.3 Sourcing of Equipment and Material<br />

Equipment supply within the EPC Agreement will be for the EPC contractor<br />

to determine, with <strong>Azura</strong> <strong>Power</strong> retaining rights of approval. The<br />

manufacturer of the gas turbines and the manufacturer of the large items of<br />

machinery will be agreed at the time of the tender for the EPC contract. <strong>Azura</strong><br />

will reserve the right to review all suppliers of major equipment and materials<br />

specified in the Bidder’s proposal or subsequently identified during the<br />

design phase, and to reject any suppliers whose equipment quality,<br />

performance or repair service has been unsatisfactory on other projects. The<br />

supply of smaller items of equipment and machinery will be mostly at the<br />

discretion of the EPC contractor with either some right of approval by <strong>Azura</strong><br />

<strong>Power</strong> or some period of extended warranty made available to <strong>Azura</strong> <strong>Power</strong><br />

by the EPC contractor.<br />

Raw materials will be sourced locally to the extent possible. Heavy<br />

equipment that is sourced externally will be transported using the main<br />

transportation route identified. The bridges on the route between Koko Port<br />

and the Project site have a proven capacity to withstand the weight of the<br />

heavy equipment required (up to 200 tonnes).<br />

AZURA EDO IPP<br />

3-18<br />

DRAFT EIA REPORT

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!