7.15.4 <strong>Impact</strong> Description and Significance: Summary<br />

Table 7.27 provides a summary of the significant impacts likely to arise during<br />

construction, operation and decommissioning prior to the implementation of<br />

mitigation measures (see Chapter 8).<br />

Table 7.27<br />

Summary of <strong>Impact</strong> Significance Pre-mitigation<br />

Phase <strong>Impact</strong> Significance (premitigation)<br />

Construction<br />

Psychological impacts related to changes in<br />

culture, unmet expectations, noise and dust<br />

nuisance, physical health and STIs and safety<br />

risks, improvements to electricity supply,<br />

health care facilities and water resources.<br />

Moderate Negative &<br />

Minor Positive<br />

Operation<br />

Psychological impacts related to unmet<br />

expectations, noise and dust nuisance,<br />

physical health and STIs, safety risks and<br />

contamination risks, improvements to<br />

electricity supply, health care facilities and<br />

water resources.<br />

Minor Negative & Minor<br />

Positive<br />

Decommissioning Ongoing effects from the operational phase,<br />

safety risks and noise and dust nuisance.<br />

Moderate Negative<br />

7.16 WORKPLACE HEALTH AND SAFETY<br />

7.16.1 <strong>Impact</strong> Description and Significance: Construction<br />

<strong>Impact</strong> Description<br />

Activities related to excavation, facility construction, heavy vehicle traffic on<br />

site and potential additional habitats for mosquito-breeding will pose risks to<br />

the health and safety (H&S) of employees. The following negative health<br />

impacts have been identified during the construction phase of the Project:<br />

• Physical health impacts due to noise and dust pollution on site;<br />

• <strong>Impact</strong>s to the physical health of employees due to infectious disease and<br />

vector and/or water-borne diseases such as malaria. During construction<br />

there will be an increased numbers of people, and in the cases that<br />

transmission is a function of direct contacts the prevalence will increase<br />

with group size; and<br />

• Physical H&S impacts resulting from any accidents occurring on and<br />

around site including trips, falls, operation of machinery, movement of<br />

plant on site and electrical incidents associated with the laying of the<br />

transmission line.<br />

AZURA EDO IPP<br />

7-78<br />

DRAFT EIA REPORT