Bridgestone Retail Operations, LLC<br />

PROJECT MANUAL<br />

Version: January 2012<br />

SECTION 01002<br />

GENERAL PROJECT REQUIREMENTS<br />

A. GENERAL<br />

1. Contractor and all Subcontractors are directed and required to read the entire project manual<br />

and Standard General Conditions included herein in order to familiarize themselves with all<br />

items related to their individual crafts.<br />

2. The BFS Retail & Commercial Operations, LLC, Standard General Conditions as part of the<br />

Contract Form are a part of these specifications and the contractors will be held responsible<br />

for their fulfillment. Non-reading of said Standard General Conditions by Contractor or<br />

Subcontractors shall not be accepted as an excuse for failure to comply with them.<br />

3. Contractor shall keep one complete up-to-date set of Drawings and Specifications on the job<br />

at all times, including all voided sheets for ready reference in addition to other copies of<br />

Drawings and Specifications used by mechanics on actual construction work.<br />

B. DEFINITIONS<br />

1. Wherever the words "Owner and Contractor” are used in this Project Manual, it refers to<br />

those entities as defined on the Contract Form.<br />

C. TERMS INCLUDED<br />

1. Any item or construction detail not shown on the Drawings but called for in the Specifications<br />

and any item or construction detail shown on the Drawings and not mentioned in the<br />

Specifications are a part of this contract just as much as if they are shown and mentioned on<br />

both Drawings and Specifications.<br />

D. CHANGES<br />

1. Any changes or additions to the Contract, Drawings or Specifications shall be in writing on<br />

Owner's "Change Order" form. Contractor and all Subcontractors are hereby given notice<br />

that no extras will be recognized unless they are authorized in writing on said form by<br />

Owner's Field Representative.<br />

E. DISCREPANCIES, CONTRADICTIONS AND AMBIGUITIES<br />

1. Any discrepancies, contradictions or ambiguities on the Drawings and/or specifications or<br />

between the Drawings and specifications shall be called to the Owner's attention at time of<br />

submitting bid and before awarding of contract. If this procedure is not followed, the Owner<br />

reserves the right to rule on any discrepancies, contradictions or ambiguities in the<br />

Drawings and Specifications after awarding of contract and Owner's decision shall be final.<br />

Contractor shall have no claim for extra compensation because of decision.<br />

2. No extra charge will be allowed on account of differences between actual dimensions and<br />

measurements indicated on Drawings. Differences which may be found shall be submitted to<br />

Owner for his consideration before proceeding with the work.<br />

GENERAL PROJECT REQUIREMENTS 01002 - Page 1 of 7