Bridgestone Retail Operations, LLC<br />

PROJECT MANUAL<br />

Version: January 2012<br />

b. Building foundation excavation and subgrade preparation shall be observed for conformity<br />

to the size, depth and suitability of the excavated areas and test for verification of the soil<br />

bearing capacity for compliance with the geotechnical recommended specified values.<br />

Porous fill shall be examined for soils classification, depth and percentage of compaction.<br />

5. Using the geotechnical engineering report as a guide, report any deviation from the<br />

recommendations contained within the geotechnical report and point out the deviation to the<br />

job superintendent. DO NOT MAKE ANY RECOMMENDATIONS FOR MEANS AND<br />

METHODS TO BE USED BY THE CONTRACTOR.<br />

6. Test and verify soil-bearing capacity of each column footing and every 30 lineal feet of wall<br />

foundation.<br />

7. Perform the following tests as necessary:<br />

a. Atterberg Limits Test – two (2) tests anticipated<br />

b. Percent Fines - two (2) tests anticipated<br />

c. Standard Proctor - two (2) tests anticipated<br />

d. Nuclear Density Gauge to evaluate bearing soils at spread footing excavation and for fill<br />

soils – ten visits anticipated.<br />

e. Hand auger and penetrometer for native soils.<br />

3.03 Asphalt/Concrete Pavement Testing Specification<br />

The Testing Specifications listed below shall be executed without deviation in accordance with the<br />

Project Drawings and Specifications. Any discrepancies between these documents will be brought<br />

to the immediate attention of the Bridgestone Retail Operations, LLC Zone Construction Manager.<br />

All reports shall be made on 8-1/2 x 11 white papers, suitable for photocopying and binding in<br />

booklet form. All sheets shall have the Testing and Engineer’s letterhead (including phone number,<br />

address and email address). Larger sheets shall be folded and bound into the booklet. Reports<br />

shall include:<br />

a. Date issued<br />

b. Project title and number as it appears on the Contract Documents.<br />

c. Name of the inspector<br />

d. Name and seal of registered engineer in responsible charge.<br />

e. Date and time of sampling or inspection.<br />

f. Identification of product and specification section.<br />

g. Location of sampling or inspection in the Project.<br />

h. Type of inspection or test performed.<br />

i. Date of test.<br />

j. Results of test.<br />

k. Indicate conformance or non-conformance with the Contract Document requirements and<br />

provide Testing and Engineer’s interpretation of test or inspection results.<br />

All tests and inspections not conforming to the Contract Documents shall be stamped with a red<br />

stamp indicating non-0conrormance and distributed within 20 hours of discovery using the red letter<br />

format attached to this document.<br />

After each inspection or test, a report shall be distributed within three calendar days to:<br />

Bridgestone Retail Operations, LLC Zone Construction Manager<br />

SITE-Work Engineering Consultant<br />

Developer or Contractor<br />

Building Official<br />

Architectural Consultant<br />

1 copy<br />

1 copy<br />

3 copies<br />

as Required<br />

1 copy<br />

QUALITY REQUIREMENTS 01400 - Page 4 of 11