Bridgestone Retail Operations LLC..<br />

Invitation to Bid<br />

j. There are several long lead Owner Furnished items that must be ordered by Bridgestone<br />

Retail Operations LLC. from several National Account Vendors. These items include but<br />

are not necessarily limited to: the Automobile Lifts or Hoists, fixtures, racking, automotive<br />

equipment, imbedded safe and key drop box etc. as noted on the F1 and F2 drawings.<br />

Most but not all items will be consolidated at a third party warehouse for release to the<br />

jobsite on the attached schedule. These five delivery dates and all dates contained within<br />

the Construction Wire, are to be included and incorporated into your Project Schedule.<br />

These deliveries and associated timelines are CRITICAL and must be achieved without<br />

any exception.<br />

k. Contractor shall only use Rotary certified RAI installers for the installation of the<br />

Rotary lifts.<br />

l. The Project Manager and or Job Superintendent assigned to manage the project shall<br />

not be changed or reassigned without written consent from Bridgestone Retail<br />

Operations LLC. In the event that any Job Superintendent is, for whatever reason,<br />

unable to work on the project, Bridgestone Retail Operations LLC has the right to accept<br />

or reject General Contractor’s promptly tendered proposed replacement and re-negotiate<br />

General Contractor’s fees. The Job Superintendent is expected to be on the job site<br />

during normal working hours M-F and come to the job site to meet with subcontractors<br />

performing night work as may be required.<br />

m. General Contractor shall maintain the highest standards of integrity and honesty in its<br />

dealings with all public authorities relating to the project. General Contractor hereby<br />

warrants that all representation it has made or will make to such authorities is factually<br />

accurate.<br />

n. The General Contractor will be responsible for the installation of all Bridgestone Retail<br />

Operations LLC. furnished equipment, fixtures, displays, furniture and inventory racking<br />

(tier racks & parts racks). General Contractor shall enter into a contract only with<br />

Bridgestone authorized fixture installers listed in Exhibit B. The following equipment<br />

will be installed (unloaded, set in place, attached to floor and plugged into a power outlet<br />

installed by the General Contractor) by a Bridgestone Retail Operations LLC. Vendor at<br />

no expense to the General Contractor: Hunter Alignment Machine, Hunter Brake Lathe,<br />

and Hunter Wheel Balancers. The New Oil Tank and associated piping and dispensing<br />

system will also be furnished and installed by a Bridgestone Retail Operations LLC.<br />

Vendor.<br />

o. Fire Alarm System and Security System shall be exclusively contracted with<br />

Stanley Security Solutions – Bridgestone’s National Account Vendor – No other<br />

installers will be accepted. (This work will be contracted directly by BSRO with the<br />

coordination and scheduling of the alarm and/or burglar alarm installation by the<br />

successful General Contractor. The contact information for that coordination is:<br />

STANLEY SECURITY SOLUTIONS<br />

Contact Person: Andrew (Drew) McLaughlin<br />

Telephone: 612.872.3453<br />

E-mail:<br />

Andrew.McLaughlin@sbdinc.com<br />

p. The job site (building interior & exterior property) MUST be kept in a clean and orderly<br />

fashion at all times.<br />

July 5, 2012 Updated New Store Invitation to Bid Revised 07-05-2012 Page 14