Bridgestone Retail Operations, LLC<br />

PROJECT MANUAL<br />

Version: Version: January 2012<br />

b. Determine that proper bearing strata is obtained and utilized for bearing and that shafts<br />

are properly clean and dry before placing concrete.<br />

c. Notify Architect if soil or water conditions require casing of piers.<br />

d. Prepare and submit inspection reports of pier drilling which shall contain following:<br />

i. Pier mark with location as established on the drawings, using grid lines as<br />

references.<br />

ii. Pier diameter and bell size.<br />

iii. Pier bearing elevation (depth) as calculated from finish floor elevation.<br />

iv. Depth of penetration into bearing strata.<br />

v. Condition of bottom of excavation.<br />

vi. Plumbness deviation.<br />

vii. Description of unusual conditions encountered, including ground water and if<br />

casing was used, size and depth of casing.<br />

viii. Size, number and length of rebar placed.<br />

ix. Record of deviations from Contract Document requirements.<br />

e. Perform concrete testing in accordance with Section 01400 Quality Requirements.<br />

3.05 TOLERANCES<br />

a. Maximum: 1" in l0' from vertical for plumb piers.<br />

b. Top: Maximum 2 inches from location indicated.<br />

3.06 WARRANTY/GUARANTEE<br />

A. Contractor shall be responsible for additional work as may be required to correct work, which<br />

does not conform to specified requirements, including strength and tolerances.<br />

END OF SECTION<br />

DRILLED PIER FOUNDATIONS 02370 Page 3 of 3