Bridgestone Retail Operations, LLC<br />

PROJECT MANUAL<br />

Version: December 2010a<br />

PERCENT<br />

Minimum Passing 1" Sieve 100<br />

Minimum Passing No. 4 Sieve 60<br />

b. Old bituminous wearing surface shall be pulverized so that 100% will<br />

pass a 2" sieve.<br />

c. During the interval of time between applications and mixing, hydrated<br />

lime that has been exposed to the open air for a period of 6 hours or<br />

more or to excessive loss due to washing or blowing will not be<br />

accepted for payment.<br />

3.07 COMPACTION:<br />

A. Compaction shall be in layers (6" maximum-loose measure) to the uniform density as<br />

shown on the drawings.<br />

B. Compaction of the mixture shall begin immediately after final mixing and in no case later<br />

than 3 calendar days after final mixing, unless approval is obtained from the Engineer.<br />

C. The material shall be aerated or sprinkled as necessary to provide the optimum moisture.<br />

D. Compaction shall begin at the bottom ad shall continue until the entire depth of mixture is<br />

uniformly compacted as hereinafter specified.<br />

E. If the total thickness of the material to be treated cannot be mixed in one operation, the<br />

previously mixed material shall be bladed to a windrow just beyond the area to be treated<br />

and the next layer mixed with lime as previously specified. The first layer of the treated<br />

material shall be compacted in such a manner that the treated material will not be mixed<br />

with the underlying material.<br />

F. After compaction and shaping the surface shall be kept wet until the paving is applied to<br />

seal the sub grade.<br />

3.08 ALLOWABLE TOLERANCES:<br />

A. SURFACE TEST:<br />

1. After the sub grade is completely compacted to required density, the surface<br />

shall be tested for smoothness and accuracy of grade as hereinabove set out. If<br />

any portions are found to lack required smoothness or failing accuracy of grade<br />

or crown, such portions shall be scarified, reshaped, recompacted and otherwise<br />

manipulated until the required smoothness and accuracy is obtained. The<br />

Contractor under the supervision of the Engineer shall make these tests.<br />

2. Density: Field density tests will be taken in accordance with the provisions as set<br />

out in Section 01400 Quality Requirements.<br />

END OF SECTION<br />

LIME STABILIZED SUBGRADE 02245 – Page 4 of 4

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!