Bridgestone Retail Operations LLC..<br />

Invitation to Bid<br />

Proceed and subsequently on the 1 st day of every month following the start of<br />

construction reflecting the current and actual status of the progress of the work, i.e.,<br />

adjusting line items, regardless of cause, those that are ahead of or behind schedule. In<br />

addition, upon the start of construction, a Project Status Report MUST be emailed to<br />

Forrest Wells and Brandy Story each and every Friday by 5:00 PM Central Standard<br />

Time indicating what work scheduled during the next 3 weeks.<br />

f. You must also provide your in-house breakdown/bid tabulation if requested by the<br />

owner.<br />

g. You must submit with your bid, the resumes of two Site Superintendents that will be<br />

available to supervise the construction of the project. The Owner reserves the right to<br />

interview each superintendent and select the one that we think will be the best person for<br />

the project.<br />

h. The project must have a full time project superintendent onsite on the job from the start<br />

of construction through Contract Completion (Store Opening), which may be as much<br />

as 30 days following Substantial Completion (Turnover for Fixture and<br />

Merchandise). The superintendents proposed for this project must have a minimum of 5<br />

years construction supervision experience within the last 7 years. Owner shall have the<br />

right to approve the project superintendent prior to construction.<br />

i. Alternates shall be itemized separately using the appropriate tab of the Bridgestone<br />

Retail Operations LLC Bid Form and are NOT to be included in the Base Bid. The Base<br />

Bid should be for the primary products specified on Plans and <strong>Specs</strong>. Owner reserves<br />

the right to accept or reject any alternates proposed by the Bidder.<br />

j. The Bid Documents include: On-site and Off-site improvements including drive<br />

approaches to street paving, utility routing etc. Your bid shall in a cover letter summarize<br />

and breakout the costs of the Building and the Site work separately.<br />

k. Payment & Performance Bonds are are not required for this project.<br />

l. Questions: Bidders shall notify the Architect and Owner in writing of any discrepancies,<br />

ambiguities, omissions, or questions concerning the Drawings and Specifications.<br />

Written requests and responses shall be made via e-mail using the Request for<br />

Information form provided with this invitation. Replies will be issued to all prime<br />

bidders of record as Addenda to the Drawings and Specifications, which will become part<br />

of the Construction Contract. The Architect and Owner will not be responsible for oral<br />

clarification. Questions received less than 48 hours before the bid opening cannot<br />

be answered.<br />

m. Owner/Developer reserves right to reject bids and to waive irregularities, technicalities,<br />

and informalities.<br />

n. You must submit with your bid a copy of your Certificate of Insurance and<br />

Contractor’s License for the state and city in which the project will be built.<br />

o. Examination: Bidders shall carefully examine the documents and the project site to<br />

obtain firsthand knowledge of existing conditions. Contractors will not be given extra<br />

payments for conditions, which can be determined by examining the site and documents.<br />

p. Subcontractors: Owner/Developer reserves the right to recommend or reject<br />

subcontractors.<br />

July 5, 2012 Updated New Store Invitation to Bid Revised 07-05-2012 Page 4