Bridgestone Retail Operations, LLC<br />

PROJECT MANUAL<br />

Version: Version: January 2012<br />

SECTION 02370<br />

DRILLED PIER FOUNDATIONS<br />

PART 1 GENERAL<br />

1.01 WORK INCLUDED<br />

a. Bored end bearing cast-in-place concrete piers with reinforcing steel.<br />

1.02 RELATED WORK<br />

a. Appendix A - Soil Investigation Data: Soil report.<br />

b. Section 01410 - Testing Laboratory Services.<br />

c. Section 02200 - Earthwork: Cut and fill to specified level and/or designated bearing<br />

elevation.<br />

d. Section 03300 - Cast-in-Place Concrete: Specifications for concrete.<br />

1.03 QUALITY ASSURANCE<br />

a. No additional requirements.<br />

1.04 SUBMITTALS<br />

a. Test Reports: Reports of all tests and inspections shall be forwarded to the Owner, the<br />

Architect, the Structural Engineer and the Contractor. Reports of tests shall state<br />

whether or not tests conform with contract documents.<br />

1.04 STORAGE AND HANDLING<br />

a. No additional requirements.<br />

PART 2 PRODUCTS<br />

2.01 MATERIALS<br />

a. Concrete Materials and Mix: Specified in Section 03300 and on drawings.<br />

b. Steel Casing: Of sufficient strength, diameter, length and construction to meet<br />

construction requirements as to safety and prevention of caving of soil and water<br />

penetration.<br />

2.02 FABRICATION<br />

a. No additional requirements.<br />

DRILLED PIER FOUNDATIONS 02370 Page 1 of 3