Bridgestone Retail Operations, LLC<br />

PROJECT MANUAL<br />

Version: January 2012<br />

C. Submit updated schedule with each Application for Payment.<br />

D. Refer to Invitation To Bid Section 15: Scheduling, for additional requirements.<br />

2.04 SUBMITTALS FOR REVIEW and/or APPROVAL<br />

A. Shop Drawings and Information will be required as listed below:<br />

1 Structural Steel and Joists (Wood structures if applicable)<br />

2 Anchor Bolt Details<br />

3 Reinforcing Steel in Concrete & Masonry<br />

4 Storefront Glazing<br />

5 Mechanical Equipment (see Section 15010)<br />

6 Interior and Exterior Luminaries<br />

7 Electrical Switch-gear and Panel-boards<br />

8 Fire Alarm<br />

9 Sprinkler (If applicable)<br />

10 Plumbing Fixtures<br />

11 Concrete and Mortar Mix Designs<br />

12 Doors & Hardware<br />

PART 3 SUBMITTALS<br />

3.01 NUMBER OF COPIES OF SUBMITTALS<br />

A. Documents for Review:<br />

1. Small size sheets, not larger than 8-1/2 x 11 inches: Submit the number of copies which the<br />

Contractor requires, plus two copies which will be retained by the Owner's Representative.<br />

2. Larger Sheets, Not Larger Than 36 x 48 inches: Submit one reproducible transparency and<br />

one opaque reproduction.<br />

3.02 SUBMITTAL PROCEDURES<br />

A. Transmit each submittal with approved form.<br />

B. Sequentially number the transmittal form. Revise submittals with original number and a sequential<br />

alphabetic suffix.<br />

C. Identify Project, Contractor, Subcontractor or Supplier; pertinent drawing and detail number, and<br />

specification section number, as appropriate on each copy.<br />

D. Apply Contractor's stamp, signed or initialed certifying that review, approval, verification of<br />

Products required, field dimensions, adjacent construction Work, and coordination of information is<br />

in accordance with the requirements of the Work and Contract Documents.<br />

E. Deliver submittals to and as designated by the Owner's Representative.<br />

F. Schedule submittals to expedite the Project, and coordinate submission of related items.<br />

G. For each submittal for review, allow 15 days excluding delivery time to and from the Contractor.<br />

H. Identify variations from Contract Documents and Product or system limitations which may be<br />

detrimental to successful performance of the completed Work.<br />

I. Provide space for Contractor and Owner's Representative review stamps.<br />

J. When revised for resubmission, identify all changes made since previous submission.<br />

K. Distribute copies of reviewed submittals as appropriate. Instruct parties to promptly report any<br />

inability to comply with requirements.<br />

END OF SECTION<br />

ADMINISTRATIVE REQUIREMENTS 01300 - Page 2 of 2