Bridgestone Retail Operations, LLC<br />

PROJECT MANUAL<br />

Version: January 2012<br />

SECTION 02210<br />

SITE GRADING<br />

PART 1 GENERAL<br />

1.01 GENERAL REQUIREMENTS<br />

A. This specification shall govern for all work necessary to accomplish shaping and<br />

grading indicated on the drawings and specified herein and shall include maintaining<br />

surface drainage during construction, finish grading and all phases of the cleanup<br />

operation. This specification is a performance specification and the performance of<br />

the completed work is the responsibility of the Contractor.<br />

B. The Contractor shall uniformly grade the entire project site to provide a pleasing<br />

appearance.<br />

PART 2 PRODUCTS -- NOT APPLICABLE<br />

PART 3<br />

CONSTRUCTION METHODS<br />

3.01 FINISHING SLOPES AND SURFACES<br />

A. The Contractor shall shape and grade the project site to conform to the proposed<br />

grade and/or sections shown on the drawings, and as directed by the Engineer. In<br />

any case, the Contractor shall grade the site to provide positive drainage away from<br />

buildings and towards roads and drainage facilities. The finished appearance shall be<br />

reasonably smooth and even (abrupt changes in slope shall not be used). The degree<br />

of finish for grading slopes shall be within a tolerance of 0.1 feet of plan grade* from<br />

either blade-grader operations, or by hand-shovel operations, as the Contractor may<br />

elect, subject to the approval of the Engineer.<br />

3.02 TOP SOIL<br />

A. See Section 02227 - Site and Parking Lot Excavation and Backfill for stockpiling<br />

topsoil and utilization of topsoil.<br />

3.03 CLEAN-UP<br />

A. The Contractor shall keep the site and structures free from accumulations of waste<br />

materials, debris, etc. caused by the work or his employees. Upon completion of the<br />

project and before requesting final inspection, the site and his work shall be "broom<br />

clean" or its equivalent.<br />

*NOTE: The Contractor shall provide finished grade 4" below plan grade in all turfed areas to allow for<br />

topsoil and sodding to finished plan grade.<br />

END OF SECTION<br />

SITE GRADING 02210 – Page 1 of 1