Bridgestone Retail Operations, LLC<br />

PROJECT MANUAL<br />

Version: January 2012<br />

3.04 Inspection Services for Asphalt Testing and Inspection shall include:<br />

a. Take one (1) core sample at the rate of not less than one every 10,000 square feet of parking<br />

lot area, but not less than three (1) cores in light duty areas or three (1) cores in heavy duty<br />

areas. Testing and Engineer shall consult with the Bridgestone Retail Operations, LLC Zone<br />

Construction Manager for locations prior to the commencement of coring. Selection of core<br />

locations shall provide the greatest amount of information for the area tested.<br />

Perform the following tests:<br />

• Compression tests in accordance with ASTM C39.<br />

• Asphalt density tests in accordance with ASTM D2950.<br />

• Extraction and gradation tests in accordance with ASTM D4074 and ASTM D71.<br />

• Measure thickness of Pavement.<br />

b. Testing during placement of asphalt concrete mixture.<br />

• Test engineer shall be on-SITE when placement begins.<br />

• Perform on-SITE density tests utilizing Nuclear Density equipment.<br />

• Record ambient temperature.<br />

• Record asphalt mixing temperatures.<br />

3.05 Concrete Testing Specifications<br />

The Testing Specifications listed below shall be executed without deviation in accordance with the<br />

Project Drawings and Specifications. Any discrepancies between these documents will be brought<br />

to the immediate attention of the Bridgestone Retail Operations, LLC Zone Construction Manager.<br />

All reports shall be made on 8-1/2 x 11 white papers, suitable for photocopying and binding in<br />

booklet form. All sheets shall have the Testing and Engineer’s letterhead (including phone number,<br />

address and email address). Larger sheets shall be folded and bound into the booklet. Reports<br />

shall include:<br />

a. Date issued<br />

b. Project title and number as it appears on the Contract Documents.<br />

c. Name of the inspector<br />

d. Name and seal of registered engineer in responsible charge.<br />

e. Date and time of sampling or inspection.<br />

f. Identification of product and specification section.<br />

g. Location of sampling or inspection in the Project.<br />

h. Type of inspection or test performed.<br />

i. Date of test.<br />

j. Results of test.<br />

k. Indicate conformance or non-conformance with the Contract Document requirements and<br />

provide Testing and Engineer’s interpretation of test or inspection results.<br />

All tests and inspections not conforming to the Contract Documents shall be stamped with a red<br />

stamp indicating non-0conrormance and distributed within 20 hours of discovery using the red letter<br />

format attached to this document.<br />

After each inspection or test, a report shall be distributed within three calendar days to:<br />

Bridgestone Retail Operations, LLC Zone Construction Manager<br />

SITE-Work Engineering Consultant<br />

Developer or Contractor<br />

Building Official<br />

Architectural Consultant<br />

1 copy<br />

1 copy<br />

3 copies<br />

as Required<br />

1 copy<br />

QUALITY REQUIREMENTS 01400 - Page 5 of 11