receipt, etc. before preparing same for submission to see that the terms check with the<br />

requirements of the specifications.<br />

3.07 CLEANING<br />

A. Thoroughly clean all fixtures, switches, panelboards and other devices and equipment<br />

furnished and set in place. All surfaces shall be properly polished and shall be free of paint<br />

and other dirt and debris.<br />

B. Touch up or refinish all equipment furnished with factory applied finishes which have been<br />

damaged during the construction of the work. Properly protect the fronts of all panelboards,<br />

switchboards and other similar equipment to prevent marring and other defacing.<br />

3.08 TESTING AND LOAD BALANCING<br />

A. Test all circuits to assure them to be free of grounds. Light and test each lamp. Prove and<br />

test energy available at the load side of disconnect switches and final point of connection to<br />

driven equipment. The contractor shall make all reasonable tests as required by the Engineer<br />

to prove the integrity of the system.<br />

B. The various branch circuits served from the lighting panel boards vary in loading. The<br />

contractor shall carefully balance the load on each phase when connecting the various branch<br />

circuits in each panelboard. When all load is turned on and the system is operating at 100%<br />

demand, the imbalance shall not exceed 10%.<br />

C. Furnish at the completion of the project or each bonafide portion of the project, a final<br />

inspection certificate from the local inspecting authority.<br />

3.09 OPERATION PRIOR TO COMPLETION<br />

A. When each and every piece of electrical and mechanical equipment is ready to operate, if it is<br />

to the advantage of the Owner or the project construction to operate this equipment, the<br />

Mechanical and Electrical Contractors under this section of the work shall allow their<br />

equipment to be operated without obligating the Owner for acceptance.<br />

B. The Owner or General Contractor shall furnish the necessary operating personnel to supervise<br />

the overall operation of the machinery, but it shall remain the Contractor's responsibility until<br />

final acceptance by the Engineer for the Owner.<br />

END OF SECTION<br />